For 1:2:4 ratio the weight of cement is 50 kgs then how many kgs are the
weight of sand and aggregate

Answer Posted / rajesh kumar

Cement= 50kg
so volumn= 50/1440 = 0.0347cum

Sand= 0.0347x2= 0.0694cum
Sand in kg= 0.0694x1600 = 111kg

Aggregate = 0.0347x4 = 0.139cum
Agg. in kg = 0.139x1700 = 236kg

Is This Answer Correct ?    8 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Technical Question of Civil Engineering

2358


What is the per cu. mt. price of ready mix in Gujarat region.?

2430


Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.

2314


What is Density of cement, sand & aggregate ?

1615


cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com

2264


VAT and CST ? Which benefits for buyer ? Why benefits?

1905


What is the strength of 1:6:12 mix?

3159


Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?

2087


how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?

2226


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2237


plz.show development and anchorage length in simple diagram.

2640


PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg

2425


I need to constructive work in amaraj batteries

1939


I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.

2510


sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience

2558