How gate result to cube for 7 day?
Formula for the cube testing?
Answer / ajmal khan
Days
--------------- X Fck
4.7+ 0.833 days
For Example M20 =
7
--------------- X 20
4.7+ 0.833*7
= 13.29N/sqmm. Aproximately 1/3rd of 20N.
We can find for any day of any grade.
| Is This Answer Correct ? | 6 Yes | 1 No |
if the slab is 2 way then,where we will put lapping upper and lower side?means near to beam or center and near to center?
What is the different type of slump test indications?
How many Sqm can laid Vitrified tiles for flooring per day per masan?
Highest compressive strength of M15 concrete that can be gained at 28 days
why top layer of block work shoud be full size if any cut block adjustable than another layer?
If we know the N - Value of soil and required bearing capacity how do we know what diameter and length of pile to be casted? How can we check whether the dia. and lenght of pile we have selected are most economical onse?
Is there a way to know the aprox shuttering qty if vol of concrete is known? any thumb rule?
In your experience what is the maximum beam length. What's beam size and also please provide column size also. Thanks.
How to calculate numbers of carpenter, fitter, mason, unskilled worker on the basis of built up area or floor plat area of building?
why demand factor less then 1 ?
1 cft concrete equal how many kgs
how to calculate stirrups length for circular column
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)