Answer / john
MTS or make to stock uses a production order as a starting
point in the process and as the cost collector. MTO or make
to order uses a sales order to initiate the process and the
sales order becomes the cost collector
Is This Answer Correct ? | 14 Yes | 2 No |
Answer / peter
1 Difference: "Make to order vs. make to stock"
A configured machine is produced for a specific customer
order. This "make to order" machine is based on the
customer demand and specifica.
A "make-to-stock-machine" is produced for an anonym
customer. Who ever has a demand for such a machine will get
it.
2 Difference: SAP-specific
The production order for a "make-to-order" machine is
linked to the customer order. All the costs will be settled
to the customer order as WIP/COS.
The production order for a "make-to-stock" machine is
linked to the material number. All the costs will be
settled to the Inventory + the production variance.
3 Difference: Material ID-Number
The "make-to-order" machine has only one material number
for a range of machines (e.g. all Audi A6) but for each
configuration SAP will create an additional "internal
object number" to specify the machine.
The "make-to-stock" machine has one material number. The
specifications are fixed. This number can be stocked on a
storage location.
WBR
Peter
Is This Answer Correct ? | 10 Yes | 1 No |
Answer / nave
mto means based on customer specific request we produce
product sale
mts customer demand planing we produce and based on demand
only we sale that product
Is This Answer Correct ? | 5 Yes | 1 No |
Answer / p bhakar rao
in MTO scenario we will produced the product after
receiving the requirment from the customer ,that means in
MTO Scenario we will produce the product specific
Requirment of customer ,after recieving the requirment from
the customer,we will create the sales order ,the sales
order will triggred the manufacturing process.
in MTS Scenario we will use it is relevent for product cost
by period scenario. in make to stock scenario we will
produce the material keeping the stock in the godown after
then customer will be entered in the system
Is This Answer Correct ? | 4 Yes | 1 No |
Explain the terms segment and cycle?
What is Down Payment? Can we create down payment for one time vendor or customer it is possible if it is possible explian?
What is depreciation? Explain the various types? : fi- asset accounting
Hi all.... Please explain to me... what G/L account should I maintain / create If I want to do the intercompany transfer asset - no revenue. and if I want to do the intercompany transfer asset - Net Book Value. What is the different between this 2 method. My company's requirement is ... 1. Transfering the asset on company A to company B, example Asset 1 - acquisition date : 01.06.2007 , acquisition amount : 1000, accumulated depreciation till 31.12.2007 : 10 so the net book value is 90, useful life 4 years the company wants to transfer this asset in company B. is it possible to transfer all the data just like I explain above : acquisition date : 01.06.2007 , acquisition amount : 1000, accumulated dep = 10
What differentiates one dunning level from another? : fi- accounts receivable
What is meant by Short period Posting?
Explain about automatic payment program and customization settings?
What are posting periods?
Please explain SAP roadmap?
What is collective processing of gl accounts? : fi- general ledger
What is an asset value date? : fi- asset accounting
How to upload asset balances in the middle of the year from legacy to SAP? Let me know full process,