Answer / pati
Repetitive manufacturing is for contineous products
manufacturing like cement, Iron & steel manufacturing.
No frequent changes in Routing.
Back flushing cab be done. i.e Automatic posting of good
issue and Gr
Less aless of posting and manual interference
The production will be continued for a period of time with
out any changes in the process.
No need of lot siges very frequently
Costin of material is done by Cost controller.
Is This Answer Correct ? | 10 Yes | 0 No |
Answer / aruldoss
repititave manufacturing done with the help of bakflush
the quantity. we can get the stock without gi & gr. with
help of MFBF we can get the stock as per our
requiremant.before that we need production versions, and
product costing,std cost estimation also done
Is This Answer Correct ? | 8 Yes | 1 No |
Answer / rtg
pre costing has been done before mrp run.
used both for make-to-stock and make-to-order
mrp run
Is This Answer Correct ? | 7 Yes | 2 No |
Answer / ramendra verma
In Repitative Manufacturing.we dont have make the BOM
frequently.The change in production process is less.It is
Quantity based planing.Material back flushing is after the
process run.
Is This Answer Correct ? | 4 Yes | 3 No |
Answer / amit malhotra
Repitative manufacturing is use for contineous process,
product costing can be calculate on BOM and process defined
and as per that back flush is carried out.
we make a ease comparision of plan and actual.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / janani
REM IS USEFUL FOR MAKING THE COSTING AND THE MATERIAL USED
WILL NOT VARY ,MOSTLY PLAN IS RUN IN THE MONTH STARTING
LESS BOMS, BUT IN SHEDULING IT WILL AFFECT WHEN BREAK DOWN
COMES FROM PLANY MAINTENANCE .
Is This Answer Correct ? | 1 Yes | 0 No |
Do you use group BOMs for engineering/design and copy or assign them to plants at implementation?
One component 2 times assign to bom
What is MTO & MTS
Difference between different strategy groups.
What are the lot size you have used?
What are gaps? Some examples?
What is mean by Standard Value, Scheduling Margin Key, Production Version, Product Cost Collector, Control Key,Demand Management.
We are trying to create purchase requisition from mrp run. We have material, info record, source list, demand in place. Mrp is always creating plan order. Why?
What is MRP group?
What is meant by payscale structure? How did you configure the payscale structure?
What are the main controls in MRP?
Integration between PP and MM Module.