what is the ratio of M10,M20,M30,M40,M50,M60 grade concrete
Answers were Sorted based on User's Feedback
Answer / shaikh soyal
M5-1:5:10
M7.5-1:4:8
M10-1:3:6
M15-1:2:4
M20-1:1.5:3
M25-1:1:2
From M30 to above, the mixed proportion as per disegn
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / abhishek kumar
M5 - 1:5:10
M7.5 - 1:4:8
M10 - 1:3:6
M15 - 1:2:4
M20 - 1:1.5:3
M25 - 1:1:2
M30 - 1:0.75:1.5
M35 - 1:0.5:1
However, it is given the mix ratio of M30 &
M35 but most of the times we preferebly use design mix for M30 and above grades. Hope this info helps you..
Thank you...!!!
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / palanimuthu
M5 1:5:10
M7.5 1:4:8
M10 1:3:6
M15 1:2:4
M20 1:1.5:3
M25 1:1:2
M30 1:0.75:1.5
M35 1:0.5:1
M40 1:0.25:0.5
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / p.nookesh
please tell me anybody the what is the ratio of
m25,m30,m35,m40,m45,m50 grade concrete.
| Is This Answer Correct ? | 6 Yes | 7 No |
Answer / sayed murtoja ali
M5 _ (1:5:10)
M7.5 _ (1:4:8)
M10 _ (1:3:6)
M15 _ (1:2:4)
M20 _ (1:1.5:3)
M25 _ (1:1:2)
M30 _ (1:1:3)
| Is This Answer Correct ? | 2 Yes | 3 No |
Answer / siva
M5-1:5:10;
M7.5-1:4:8;
M10-1:3:6;
M15-1:2:4;
M20-1:1.5:3;
M25-1:1:2;
M30-1:1:3;
| Is This Answer Correct ? | 2 Yes | 4 No |
Answer / naveen sen
M10 - ( 1 : 3.92 : 5.62)
M20 - ( 1 : 2.48 : 3.55)
M25 - ( 1 : 2.28 : 3.27)
M30 - ( 1 : 2 : 2.87)
M35 - ( 1 : 1.79 : 2.57)
M40 - ( 1 : 1.67 : 2.39)
M45 - ( 1 : 1.58 : 2.26)
M50 - ( 1 : 1.44 : 2.23)
| Is This Answer Correct ? | 5 Yes | 14 No |
How much percent of steel use in concrete members etc.slab,beam,lintal,colmn,raft fondation according to concrete volume? Kindly reply me I am in dbout plz
what is meant by belt in house construction?
calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum
A bill was raised by contractor which read as follows 1.) Excavation in normal soil upto 1.5m - 250 cum 2.) Excavation in normal soil 1.5m to 3m - 240 cum 3.) Excavation in soft rock - 350 cum 4.) Excavation in hard rock - 250 cum 5.) Filling with available soil - 825 cum 6.) Filling with bought out soil - 1100 cum How can I verify the above quantities, especially for item no. 5 & 6? What checks are necessary before releasing the bill ?
Rate analysis of Vitrified tile in cement mortor 1:3
0 Answers Design Space, Muthoot Group,
What is the least count of Theodalite survey?
Describe Briefly The Various Methods Of Concrete Curing?
what do you mean by punching shear?
sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.
how to find quantity of concrete in PCC M15
how much steel in one sq m slab?
6 Answers J Kumar, Jaitly Associates, L&T, MEIL, Super House, United Nations Office for Project Services (UNOPS),
why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 days..
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)