Why we stop the concrete in 1/3 rd of span length
Answer / anuranjan kumar
after l/3 tesion zone develope in mid span so always stop concreting with in l/3
| Is This Answer Correct ? | 13 Yes | 2 No |
calculate the cost for AAC block wall of 15cum?
How to calculate material and labor required for 100 m2 plaster?
how to cal 1:4 in brick masonary work cement and sand?
How we can calaculate materials required for block work(1m3) block size 33cm x 20 cm x 17 cm, mortar 1:6
in the construction of residential building what type of tank are used?where?why & what is its purpose?
material used for mendrel use to bend epoxy coated rebar
1 Answers Saudi Aramco Shell Refinery Company SASREF,
what is meaning of GSB? properties, ingradiant of GSB?
for 100sft of Cement plastering ratio 1:6 How much quantity of cement and sand required.
6 Answers J.K. Organization, L&T,
Define What are the materials used in building a gravity dam?
i want to know the easy way to find the quantity of steel in a slab , coloumn
In the roof of a pumping station explain briefly the components of a waterproofing system?
explain the advantages of total stasion
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)