M5 1:5:10
M7.5 1:4:8
M10 1:3:6
M15 1:2:4
M20 1:1.5:3
M25 1:1:2
M30 1:0.75:1.5
M35 1:0.5:1
M40 1:0.25:0.5
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What are the responsibilities of a site manager?
what are the ffactors you considered choosing the course?
what is pqc
How do you change a dimension value in solidsworks?
How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
How will be cutting in timber plate size 600*400 column size
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
Volume of 25kg putty bag & 40 kg putty bag volume??
how much percent are used 20mm,10mm?
What is Density of cement, sand & aggregate ?
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
Did any of the egyptian pyramids ever fall down?
What is gravity flow?
what is the productivity in aluminium shuttering per day