for 1cum how much bag of cement is used for M20 grade
Answers were Sorted based on User's Feedback
the ratio of M20 is1:1.5:3
so bag is requred to 7.96 bag
| Is This Answer Correct ? | 37 Yes | 8 No |
Answer / raichand s.
M20 Grade is 1:1.5:3
Total quantity- 1cum
Total mix- 1+1.5+3=5.5
Apply Voids 54% i e
cement quantity={((1*1.54*)/5.5)=0.28CuM
so volume of 1 bag cement is 0.035CuM
Required bags=0.28/0.035 = 8 Bag cement
| Is This Answer Correct ? | 15 Yes | 3 No |
Answer / pramod vs gowda
The mix proportion is 1:1.5:3
We find out the quantity of cement for 1cum
Dry co-efficient of cement is 1.52
Unit weight of cement 1440
Then
(1/(1+1.5+3))*1.52=0.276
0.276*1440=397.44kg/m3
1 bag cement is equal to 50 kgs
397.44/50=7.9488
So Approximately 8 bags of cement is for 1cum
| Is This Answer Correct ? | 12 Yes | 1 No |
Answer / shaik mahammad sharif
For M 20 grade Concret 1:1.5:3 ratio is required
1 is Cement, 1.5 is Fine Aggregate and 3 is Coarse Aggregate
Add 50% of wet cement concret =1.55 Cubic M
Cement Require for Cub M =(1.55/(1+1.5+3))*30=8.45 Bags
Sand =0.281*1.5=0.42 Cub M
Meterial =0.281*3=0.84 Cub M
| Is This Answer Correct ? | 5 Yes | 1 No |
Answer / raju sardar
As per the CPWD material consumption constants, 8.4 bags of
cement.
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / deep dubey
it depends on mix . its design mix or nominak mix.
in nominal mix 8 bag and in designmix we use 270 to 320 kg.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / mohan kumar
ratio 1:1.5:3
total mixing =1+1.5+3=5.5
area 1 cu m
(1/5.5)1.56*1=0.284 cum
=0.284*1440
=408.94 kg/cum
=408.94/50
=8.17 bags
| Is This Answer Correct ? | 0 Yes | 3 No |
what is 3.14 indicates for cutting length of stirrups
how to cement bag calculate m25 grade
List out the diameter of series of bar for beam, column, slab and footing?
Project at andheri west mumbai total area of 116000 sq ft near by..Please help me out for quotation plan is ready basic details are with me , please help me out .I will mail u in autocad also.
what will do when 7days concrete has failed and structure has constructed?
how we can calculate the quantity of sand & cement & also Aggregate so give me to this answer for a slab Length is : 25' /3.28 = 7.62 Mtr Width is : 30' /3.28 = 9.14 Mtr Depth is : 0.6"/3.28 = 0.15 2Mtr
how many Concrete hollow blocks (6"x8"x16") will one mason and one helper accomplish/Install a day (8 hrs/day)?
5 Answers Gabriel Construction,
Which is code is used for measurmenr of reinforcement steel work.
in the footings first which reinforcement bar has to be layed as per design criteria.
how to remove the quantity of metal 1 and metal 2 in concrete
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
what is the used civil engg?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)