If process order is technically closed, by mistake
I want to process that order again can I do it?
Answers were Sorted based on User's Feedback
Answer / bharathish
First you have to do revoke Teco and then process the
order,other wise system wont allow..
Is This Answer Correct ? | 18 Yes | 0 No |
Answer / ajit kumar santi
First thing is that Technically closed is word.
Technically complete (TECO)is a status and Closed (CLSD) is a status.in case of TECO you can revoke TECO right there.
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / harikrishna
i did not get this help me ..to understand the q and ans both
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / shivshankar
yes u can do Posting even if order is TECO.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / arun k
If order is in teco status , then this order is irrelevant to mrp , all purchase requisation and planned order is cancelled for that order and capacity also cancelled for that order, first you need to do the revoke teco and process it
Is This Answer Correct ? | 0 Yes | 0 No |
Describe the process for creating and adding to material BOMs. Include release procedure/status, notifications, responsibilities, authorizations, involved systems, Engineering Change Management, and so on.
Tell some sop
What are all the steps involved in Variant Configuration?
Explain the process of Material costing.
How many types of SOPs are there?
while extending the material master view after saving error is coming that the field material number is defined as a required field,it doesnt contain an entry. After selecting that it is showing the particular material may be locked. Pls do the needful.
What is the planning time fence?
What are basic dates?
What is activity type and how it works in costing?
Explain why there is need of production version?
Difference between Routing, Ref op set, Rate routing and Ref rate routing.
how to create report in sap pp