If process order is technically closed, by mistake
I want to process that order again can I do it?
Answer Posted / bharathish
First you have to do revoke Teco and then process the
order,other wise system wont allow..
| Is This Answer Correct ? | 18 Yes | 0 No |
Post New Answer View All Answers
how many times pcc can run for one material?
Explain different inspection type you used .
What are all the ‘technical types of bom’?
Define gaps.
Tell some standard order types and what configure done for current project
What is Schedule Margin key. How floats works in scheduling?
Mention what is the t-code for changing production order and to display production order?
What is activity type and how it works in costing?
Explain what is prt (production resource tools) in sap pp?
What is the Difference between TECO and CLSD?
What do we do in the realization phase?
What is the transaction code to run MRP for sales order?
Special Procurement type 40 – proc. form alt. plant
Difference between base unit of measure, production unit, order unit