If process order is technically closed, by mistake
I want to process that order again can I do it?
Answer Posted / ajit kumar santi
First thing is that Technically closed is word.
Technically complete (TECO)is a status and Closed (CLSD) is a status.in case of TECO you can revoke TECO right there.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
Why is work scheduling required for semi finished and finished products?
What are all the settings done for configuring the integration of pp with fico?
In implementation stage tell some standard scenario before AS-Is & TO-BE
what is the major ticket in your experience
Integration between PP and SD module.
Why the work scheduling view is required for semi-finished and finished products?
What is Material status and which view of the material master it is available?
How requirements( pir,sles order, customer requirement) are reduced after they are produced?
Can't one material be assigned to more than one operation in a routing, why?
Why and how you calculate WIP?
In lsmw which is most important step?
What is MRP group?
What is meant by payscale structure?
Explain what is the need of mrp list if the stock requirement list is already given?
what is group bom? Is it possible to attach the drawing for a material to bom? How?