I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?

Answer Posted / baskar

7 days

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the maximum crushing load in Kg & crushing strength in N/mm2 for M25 & M 15 Grade concrete

6252


what is the calculation of raw material for 0.35cum of m-15

1035


What is the snap size in civil and how can we create it?

2304


what is constat for brickwork

1683


How to calculate construction cost of residential building in mumbai

1468






which has high compressive strength between hollow block and brick masonry?

1851


how much shouid be the rate for ready mix concrete per cubic meter

1459


HDPE pipe standard bends using for TSE irrigation? is it possible to use 30 degree?

1732


1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?

6100


Why Is Propping Required For Long Structures Once The Form Work Is Removed?

694


what is the function of GSB all class ?

668


Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.

2767


what is the permanent solution applied for restoration of leaning tower of pisa?

3055


quantity of material needed for rubble stone masonry for 1:4 and 1:6

1218


Define What is a kip?

722