I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answer Posted / nagori salim
Completely depends upon Grade of Concrete
Higher the Grade, Lesser will be the period for deshuttering
| Is This Answer Correct ? | 7 Yes | 6 No |
Post New Answer View All Answers
What in your past experience or education prepares you for the position for which you are applying
why we can use dust in concrete insted of fly ash
What is the effect of a building collapse?
percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters
how to clculate the %of concrete strenght achive after curing?load
Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
Can we use concrete of slump cone in cube casting in which we have already measured slump?
Why are steel plates inserted inside bearings in elastomeric bearing?
Volume of 25kg putty bag & 40 kg putty bag volume??
what r you reqired for concrete baching plant?
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
what are the types of design? which type of method is used at what type of design & why?
what are the challenges of being a team leader and a supervisor?
how much used soil in 1 brick of standard size?