I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answer Posted / koti reddy allu
Hi Veeramani, it's Reddy here. First of all the basic
criteria for De shuttering is 1. Type of formwork i.e.
Vertical Form work for Columns, Soffit form work for
Slabs/Bems etc 2. The Effective Span of the member
Deshuttering period neither depends on Grade nor Depends on
Curing period according to IS 456 - 2000.
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
how many digree of freedom in four bar chain
can we compare the combined core of DBM and BC density with average density of Lab DBM and Lab BC density
What is the meaning of a blue land surveyors flag?
What are the responsibilities of a site manager?
Special thing in designing a overhead reservoir ? which is different from an ordinary design
Define aligned dimension?
How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9
What is the use of water table & Kreb stone for drain
Which are the top apps for you civil engineering?
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
How to avoid fly ash seed ball formations in the concrete mixer while mixing of raw materials for fly ash block manufacturing?
If we don't have drawing for Excavation of building,At what rule we will go for excavation and how much depth will go for a villa?
What is an object snap mode?
Howmuch bend to be provide for 200/600 BEEM
Why does the pressure increase under soil?