I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answer Posted / k chiranjeevulu
to remove shuttering after 14 days
| Is This Answer Correct ? | 32 Yes | 6 No |
Post New Answer View All Answers
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
what is total volume of ingredients used in concrete accordingly
How to decide/consider the grade of bitumen for dbm.
What is the strength of 1:6:12 mix?
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
any book or article on pumped concrete.
Which is the latest version of solidsworks?
what is the difference between prime coat and tack coat in road construction
how to calculate the chair reinforcement length in slabs, footing or anywhere??
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
what are the duties of Site Engineer in work site?
what is the function of GSB all class ?
Soil bearing capacity formula