I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answer Posted / vipin sharma
As per IS 456:2000, the slab shuttering can be removed
after 3 days but immediate after removal of shuttering
proping of the slab need to be done and for beam the
shuttering can be removed after 7 days subject to proping.
Advisable
slab shuttering removal- 7days
Beam bottom less than 6 meter- 14 days
Beam bottom greater than 6 meter- 21days
Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor
what is education Cess.
how to calculate valuation for the old building?
what is features of a typ-ical modern air-conditioning installation?
Different sizes of Hollow blocks and its weight. Thanks.
How did the romans get water up hills using aqua ducts?
how statics is different from dynamics
What is the yield of 100 litres of water and 10 kg of cement in grout mix?
at which depth the construction of tunnel is economical from cost and engineering aspect.
In block work seawalls what is the purpose of slip joints?
What is the largest concrete dam in the world?
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
How to calculate paint drums per meter square
1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.