I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?

Answer Posted / vipin sharma

As per IS 456:2000, the slab shuttering can be removed
after 3 days but immediate after removal of shuttering
proping of the slab need to be done and for beam the
shuttering can be removed after 7 days subject to proping.
Advisable
slab shuttering removal- 7days
Beam bottom less than 6 meter- 14 days
Beam bottom greater than 6 meter- 21days

Is This Answer Correct ?    3 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor

1752


what is education Cess.

1738


how to calculate valuation for the old building?

1807


what is features of a typ-ical modern air-conditioning installation?

1495


Different sizes of Hollow blocks and its weight. Thanks.

1919






How did the romans get water up hills using aqua ducts?

797


how statics is different from dynamics

1234


What is the yield of 100 litres of water and 10 kg of cement in grout mix?

1575


at which depth the construction of tunnel is economical from cost and engineering aspect.

1307


In block work seawalls what is the purpose of slip joints?

750


What is the largest concrete dam in the world?

683


do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?

1230


If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.

1538


How to calculate paint drums per meter square

2014


1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.

2698