explain BOM usage and status?
Answers were Sorted based on User's Feedback
Answer / rasika deshpande
By means of BOM usage, you can manage separate bills of
material for various internal organizational areas
(engineering/design, production, costing, and so on).We can
define different boms for the different areas of the
company, such as design dept, production, sells and
distribution etc. , depending on their individual
requirement. This can be done by choosing different usages
while creating the bom.
The BOM status specifies whether a bill of material is
active or inactive for different organizational areas.
it can be seen at header level of the bom.
Is This Answer Correct ? | 13 Yes | 4 No |
Answer / atul y
The bill of material usage specifies the departments or
functions within a company where the bill of
material is used.
The BOM status controls BOM processing in different
application areas
Example:
BOM X:
BOM with status '1' can be exploded in MRP and released for
a planned order.
BOM Y:
BOM with status '2' cannot be exploded in MRP or released
for a planned order.
Is This Answer Correct ? | 5 Yes | 1 No |
Answer / venkatesh
Bill of Material is the quantity details of each item used
for producing a finished product.
Is This Answer Correct ? | 1 Yes | 4 No |
What are all the ‘technical types of bom’?
I have created an order type “ZYC6”, how I know that which types of order it is like process, production or SD order?
Describe control key utility & also standard key ? how many fields can be configured for standard value key?
Why and how you calculate WIP?
define variable cost
my scenario is repetitive manufacturing (REM) make-to-stock (MTS)production for sugar industry. What are the things, I have to customize for this scenario, to the PP point of view..
Define stock requirement
What is MRP group?
Do you have several alternative BOMs for a material, depending on the manufacturing procedure or lot size, for example (multiple BOM)?
Mention what is the difference between stock transport order and stock transfer order?
Describe the change process for material BOMs. Include release procedure/status, notifications, responsibilities, authorizations, involved systems, engineering change management,revision levels, synchronization with current production orders, other.
What is the difference between “planned consumption” and “unplanned consumption”? Can safety stock calculation be done on either of these?