explain BOM usage and status?
Answers were Sorted based on User's Feedback
Answer / rasika deshpande
By means of BOM usage, you can manage separate bills of
material for various internal organizational areas
(engineering/design, production, costing, and so on).We can
define different boms for the different areas of the
company, such as design dept, production, sells and
distribution etc. , depending on their individual
requirement. This can be done by choosing different usages
while creating the bom.
The BOM status specifies whether a bill of material is
active or inactive for different organizational areas.
it can be seen at header level of the bom.
Is This Answer Correct ? | 13 Yes | 4 No |
Answer / atul y
The bill of material usage specifies the departments or
functions within a company where the bill of
material is used.
The BOM status controls BOM processing in different
application areas
Example:
BOM X:
BOM with status '1' can be exploded in MRP and released for
a planned order.
BOM Y:
BOM with status '2' cannot be exploded in MRP or released
for a planned order.
Is This Answer Correct ? | 5 Yes | 1 No |
Answer / venkatesh
Bill of Material is the quantity details of each item used
for producing a finished product.
Is This Answer Correct ? | 1 Yes | 4 No |
Tell some standard order types and what configure done for current project
What is advantage of repetative manufacturing ?
What does a PP Consultant do in his/her real time?
Explain Flexible planning Procedure?
What are the types of master views for production and planning?
What are the key fields in MRP views?
Explain source inspection.
What is the output of mps run ?
What change management functions do you require? How do you want to define the validity of BOMs (based on date/freely definable parameters)? Must existing change histories be transferred to the R/3 System?
what is standard info set? where it is used in pp?
what do you mean by opening periods
Explain the uses of the simple maintenance interface?