Answer Posted / rasika deshpande
By means of BOM usage, you can manage separate bills of
material for various internal organizational areas
(engineering/design, production, costing, and so on).We can
define different boms for the different areas of the
company, such as design dept, production, sells and
distribution etc. , depending on their individual
requirement. This can be done by choosing different usages
while creating the bom.
The BOM status specifies whether a bill of material is
active or inactive for different organizational areas.
it can be seen at header level of the bom.
| Is This Answer Correct ? | 13 Yes | 4 No |
Post New Answer View All Answers
What are the key fields in MRP views?
What does the use of ms70 followed by mcec get you?
Explain Flexible planning Procedure?
In the monthly lot size proc, how to generate lot at the end of Period?
We need to do gi of components to production order using back-flush. The component stock is managed in batches. The batch to be back-flushed?
How system calculate the actual cost?
Explain Flexible Planning procedure or How many levels of Flexible planning.
What is Phantom Assembly?
In implementation stage tell some standard scenario before AS-Is & TO-BE
Difference between different strategy groups.
Mention what are the production process in sap?
We have two storage locations are ‘0001’ and ‘0600’. Default storage location in process order is always ‘0001’ what determines this default location?
What do we do in the realization phase?
How can you get planned orders scheduled so that you can do capacity leveling ?
What are the types of MIC?