Explain handled go live activities-Dry run,Cut over
activities & post go live Support
Answer / dantham conpolwedson
Dear All,
The sequence of the activities given is as follows,
Dry Run
Cut Over
Go Live
Post Go live Support.
In Dry Run the business activities that are configured in
system are given to user, for testing and evaluation,
training etc. In this case the existing system runs
parallel to the new system, so as that no business are
hampered, as well as accurate results are achieved.
In Cut Over, a call is taken from both the point of view,
i.e. system and business, that old system is to be cut off
and new system will take over the activities. However few
business tend to run both the system parallel till a
confidence level is build, and end results are same as both
the systems are concerned. But in Cut over, user does not
expect too much from the old system.
In Go Live, the old system is stopped, stock are taken into
the system, accounts values are books of accounts are same
as old system, from where the new system will take over
from the old system, old system may refer to legacy data
for references but, so far as the current activities are
concerned, they take place in the new system, the old is
for reference only.
Post Go live Support, this involves support activities
after the Go Live has been successfully done. This may
involve, new developments, reports.
Please correct me, if there is any mistake in the answer
given.
Regards,
Dantham Conpolwedson
Is This Answer Correct ? | 29 Yes | 1 No |
Hi, experts pls answer this question, thanx in advance. if we create a functional specs for any enhancement, we need do give the approach on particular issue. could u explain how we need to find the issue and what is approach on this. for eg: if we want to copy PO no. from quotation into order,Here what is the way to find the include(routine) to create functional specs.
What is the difference between cash sales and rush order?
What is header condition type and in sales order how header condition type gets it value? Do we maintain access sequence for header condition types?
what is requirement class and requirement type? and what is the difference between them
what is pmin
Where you monitor job ,suppose you got a ticket like when machine shows a job is not run today , can you please check and let me know ,where you want to check this ?
How to create production order from sales order automatically, what are the configuration?
what do u mean by exclusive in access sequence?
Hi can some one post on interview questions& answers on CIN relevance to sd
What copy control is and when copy control transition can be done? In what manner copy control transition can be done?
Mention what are the two places where you need to configure cin (country version india)?
Hi I am preparing for interview(sap sd). In my preparation i am seeing allinterviws.com and sdn.sap websits and Glen c williams book and my tution notes. Is it enough for preparation for an interview. Pls suggest me if there r any other way to prepare. Thank u. Regards, Ramesh