Explain handled go live activities-Dry run,Cut over
activities & post go live Support
Answer Posted / dantham conpolwedson
Dear All,
The sequence of the activities given is as follows,
Dry Run
Cut Over
Go Live
Post Go live Support.
In Dry Run the business activities that are configured in
system are given to user, for testing and evaluation,
training etc. In this case the existing system runs
parallel to the new system, so as that no business are
hampered, as well as accurate results are achieved.
In Cut Over, a call is taken from both the point of view,
i.e. system and business, that old system is to be cut off
and new system will take over the activities. However few
business tend to run both the system parallel till a
confidence level is build, and end results are same as both
the systems are concerned. But in Cut over, user does not
expect too much from the old system.
In Go Live, the old system is stopped, stock are taken into
the system, accounts values are books of accounts are same
as old system, from where the new system will take over
from the old system, old system may refer to legacy data
for references but, so far as the current activities are
concerned, they take place in the new system, the old is
for reference only.
Post Go live Support, this involves support activities
after the Go Live has been successfully done. This may
involve, new developments, reports.
Please correct me, if there is any mistake in the answer
given.
Regards,
Dantham Conpolwedson
| Is This Answer Correct ? | 29 Yes | 1 No |
Post New Answer View All Answers
Differentiate between shipping point and loading point.
How to change chart of accounts of company code after making several sales orders and delivery?
What are the responsibilities of a functional consultant in an implementation project?
Hi SD Gurus, what are the documents in which we use Output Determination starting with Sales order? Where do we use the output determination? I have been asked this question in a recent interview? It’s Urgent!!!!!! I have interview within 1-2 days? So, I request you to provide solutions to above question as early as possible? Your timely help would be greatly appreciated? Thanks in advance Regard
In back order process system follows backward scheduling or forward scheduling? please give ur valuable answers
Can you make texts mandatory for a customer master or a sales document?
What is a 'customer-material information record'?
When we include a new customer, we have to maintain condition record every time or there is a process by which we can validate the condition record to that new customer belonging to the same sales area?
Can anyone tell me the link for interview question for SD module. . . As i m fresher so i really need to know what sort of question i will to have face during interviews . . . .
What is delivery document?
IF u have worked on EDI IDOC, while sending PO to vendor how u connect to the system. Tellme the entire design and steps of the screen. how it looks.When i told we need to create port, partner profile, outbound idoc process. Interviewer not satisfied.
A Client wants to connect his SAP ECC system to his SAP CRM system. What do you want to do to enable the integration?.
Maintaining sales organization (tvko)?
What happens when a value is not entered for a manual and mandatory condition type and does a header condition type have an access sequence?
Can you deference between contract & scheduling agreement?