In General Business scenario we use cost center for cost
collection and for short term or special purpose we use
Internal order. If we use Internal Order insteed of cost
center accounting so what happend. any data volume or
periodic lost data we face.
Answer / sappie
Internal Orders are interim Cost collectors. During period
end closing in Contolling, the cost from Internal orders
should be settled to other Cost Centers, COPA or Profit
Centers. Hence we can't replace cost centers with Internal
orders.
Is This Answer Correct ? | 3 Yes | 0 No |
Assign different no. range for different business area of same co. code.
Apart from vendor, customer where do we use Terms of payment.
In sap how input and output taxes are taken care?
We have total 5 branches at the time of posting document we did't specify which branch it is. Here the problem is how to know for which branch belonging it please give me answer as soon as possible thanks to all........
What is unit testing,Integration testing,Regression testing?
At the time of sap implementation what are the basic details required by CO guy, SD, MM, and PP guy from a FI guy...?
what is the difference between costing based and acconting based in copa ?
How can you default certain items while creation of internal order master data?
What is cutover data and when will you upload to production client? whether before go live or after go live?
Which is the documentation or link need to refer for the FI implementation experience?
Where are payment terms for vendor master maintained?
Difference between statistical key figure and activity type?