What is meant by 'zero value' in quantity surveying.
Answers were Sorted based on User's Feedback
Answer / sathy
Difference between BOQ cost (As per agreement) and Actual
cost (after getting the project)
| Is This Answer Correct ? | 91 Yes | 13 No |
Answer / bhanu prakash
Zero Value in Quantity Surveying is value where we are
starting the work of Surveying. i.e . the initial position
or starting point of Survey.
| Is This Answer Correct ? | 23 Yes | 9 No |
Answer / ilayaraja
Difference between BOQ cost and actual cost.
| Is This Answer Correct ? | 14 Yes | 2 No |
Answer / bharath m,+91 8438238335/99806
Zero Value is the actual cost workings for entire project,prior to start the project.
Bharath M
+91 8438238335/9980644165
| Is This Answer Correct ? | 13 Yes | 2 No |
Answer / sudheer
Zero value is BOQ cost. It will be compared with actual or
executed cost. Which show the extra cost for for
construction.
| Is This Answer Correct ? | 10 Yes | 9 No |
Answer / sameer kashmiri
The difference of initial estimated cost and final estimated cost or Actual cost should be zero or near to zero.... its called ZERO VALUE
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / balakrishnan
Zero Cost is the actual cost of each activity, in which Over heads & Profits are not included.
BOQ rate is the price which includes Over heads & Profits.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / irfan vadla
zero value is starting value which define certain calculation of quantity surveying
| Is This Answer Correct ? | 2 Yes | 3 No |
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
how to calculate triangular ring cutting length
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
How much concreat we make by 1 bag cement? (ratio- 1:1.5:3 or 1:2:4)
2 Answers Castles Consulting Engineers, KCP, Opaque Infrastructure,
how to calculate the required qantities of cement, Sand and aggrigate to prepare 1 Cum of concrete mix 1:2:4
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M hight 3.75 meter 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
How many steel is require in one cubic meter area?
what is development length,where it is used and why it is used?
what is the difference between site engineer & site incharge
what is the praposion of M30 concrete mix.
Mention what are the composition of a landfill?
Explain major difference between auto level and dumpy level?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)