How to configure the planning calendar for the ATP
calculation where goods are shipped every other working day?
Answers were Sorted based on User's Feedback
Answer / guest
Use Transaction MD25 and define calculation rule for every
other working day. Check the lot size settings in OMI4 and
maintain relevant data in MMR.
Is This Answer Correct ? | 5 Yes | 0 No |
Have alternate working days in the plant calendar attached
to the corresponding Shipping point
Is This Answer Correct ? | 0 Yes | 0 No |