how many bricks are required for masonary trench having
length of 31 mtr, depth of 0.6 mtr and breadth of 0.45 mtr
on single brick work as well as double ( 9" ) brick work

Answers were Sorted based on User's Feedback



how many bricks are required for masonary trench having length of 31 mtr, depth of 0.6 mtr and brea..

Answer / arpit garg

we need to have 3905 bricks.

Is This Answer Correct ?    6 Yes 2 No

how many bricks are required for masonary trench having length of 31 mtr, depth of 0.6 mtr and brea..

Answer / amit

4219

Is This Answer Correct ?    2 Yes 2 No

how many bricks are required for masonary trench having length of 31 mtr, depth of 0.6 mtr and brea..

Answer / suresh s sonone

4185 nos req

Is This Answer Correct ?    1 Yes 1 No

how many bricks are required for masonary trench having length of 31 mtr, depth of 0.6 mtr and brea..

Answer / gaurav kango

The total volume of masonry is 8.37 cubic meter .
So 500 no of bricks are requird for 1 cubic meter .
8.37×500= 4185
4185 no of bricks are required .

Is This Answer Correct ?    1 Yes 1 No

how many bricks are required for masonary trench having length of 31 mtr, depth of 0.6 mtr and brea..

Answer / tarique08

Total volume is 8.37 m3
So 406 nos of bricks are required for 1m3
8.37×406=3399 nos of bricks are required

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

For 12mm thick and cement plastering 1:6 on 100sqm new Brick work the quantity of cement required is

1 Answers  


1. why we use inverted beam ? 2.why we use extra bar in beam ? 3.dimension in L-bar in column ,footing and beam

2 Answers  


what motivates you to do a good job

2 Answers   Flextronics, HPCL, ISRO,


why we use min. 12mm dia bar in a coloum.

7 Answers   BPCL Bharat Petroleum,


what is the ingredient value of 40mm and 20mm aggregates?

1 Answers   Nexus Technologies, Power Grid,


how to conversation of all construction material in to brass

2 Answers   L&T, Lafarge,


How can we compact the soil on slope portion? What is the Grade II of Stone Metal?What type tests carried out on BBM road?

1 Answers  


Where are u provide laps in columns & beams?

4 Answers  


How to calculate the steel for 392c.meter*450c.meter rcc slab

2 Answers  


a butt weld is specified by

1 Answers  


What do you mean by bond? What are the different types of bonds?

1 Answers  


At which temperature in deg Celsius Asphalt is used for the pavement of Roads?

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)