Answer / shraddha
assume volume of brick masonary=10m3
dry volume=35% more=3.5 cu.m.
1.volume of cement=(3.5/7)*1=0.5cu.m
2.volume of sand=0.5*6=3 cu.m
3.no.of bricks=(10/0.004)=2500 No's
| Is This Answer Correct ? | 5 Yes | 9 No |
ONE PART OF CEMENT OR LIME & SIX PART OF FINE AGGREGATE.
| Is This Answer Correct ? | 6 Yes | 21 No |
Why is cover provided in beams, slabs, lintels, columns, etc ? What is the drawback of not providing cover in the same?
If in a structure, e.g, 20mm steel bar is not available and we use 16mm steel bar instead of 20mm bar, how can we calculate the no. of steel bars for 16mm diameter bar?
How to calculate steel quantity in beam and column?
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
structural engineering based
what is the density of Coarse Aggregate in 1 cu m of Concrete?
How Much the Lean concrete Density?
0 Answers Techno Unique Infratech,
In which direction is bottom bar of rectangular footing is placed in short or long.
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
why does the most of civil engg is not intersted to going for teaching field?
what is mean by hysd bar?
what is the difference between factor of safety and partial safety factor.??
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)