how much quantity of blocks, cement and sand is required to
complete 1sq.m of CC Hollow blockwork. Size-16"x8"x8". Also
what is the cement sand ration commonly used?

Answers were Sorted based on User's Feedback



how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / k.amirthalingam

Quantity of material used for a Hollow block work
(400X200X200)?

1. Qty of HOllow block is 10 to 12 numbers / Sqm
2. Cement sand ratio preferable is 1:4
3. For 1:4 CM the cement, sand calculation as follows

Volume of mortor = Horizontal joints 5 rows of 200 mm wide
20 mm thick = 5*.2*.02 = .02 cum

Volume of verticaljoints : 5*2.5*.2*.2*.02 = .01 cum

Total = .03 + 30 % wastage = 0.039 Cum of Cement Mortor

For 1:4 ratio

Weight of cement in 1 Sqm = .039*1*(1/5)*1440 = 11.232
Kg /Sqm

Volume of Sand = .039*1*(4/5) = .0312 Cum = 1.11 Cubic foot


NOTE: But in actual it occurs more than the above
calculated values because many unskilled people filling the
hollow portions of the block. This is the wrong practice.
The Laying system is such that the hollow portion to be
overlapped with filled portion hence the hollow portion to
be maintained. This will give good heat reduction inside
the building.

For more queris mail me at ameerabic@gmail.com

K.Amirthalingam from Ariyalur

Is This Answer Correct ?    134 Yes 47 No

how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / balamurugan

1.Qty of Hollow block is 11 to 12 Nos/ sqm
2.For 9" wide wall Cement sand ratio is 1:6 & 4" wide wall
Cement sand ratio is 1:4.

Volume of mortar/Sqm = (No of Blocks required for the size
of without mortar thick -No of Blocks required for the size
of block including mortar thick)x No of Blocks required for
the actual size of block

For 9" wall

No of Blocks required for the size of without mortar
thick=1/(0.40*.20*.20)=62.5
No of Blocks required for the size of block including mortar
thick= 1/(0.41*.21*0.21)=53.31 Nos

Volume of mortar/Cum= [62.5-55.31]x[0.4x0.2*0.2]
=0.115 Cum
Add wastage 30% extra

Volume of mortar/Cum= 0.115*30% =0.150Cum

Cement sand calculation/Cum of Block work:

Ratio 1:6

Cement =[1/7*1440]*.150 =31Kg
Sand =[(6/7)*.15]=0.129Cum =4.55 Cft

Cement sand calculation/Sqm of Block work:

Ratio 1:6

Cement =[1/7*1440]*.15*.23 =7.13Kg
Sand =[(6/7)*.15*.23]=0.03Cum =1.05Cft

Is This Answer Correct ?    80 Yes 39 No

how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / estimator

1. the quantity of CHB required per sq.m. is equal to area to be filled divided by the area of CHB
= 1 sqm / ( 0.4x0.2 ) = 12.5 CHB, approx. 13 CHB (16"x8"x8)
2. computing the mortar required using the density of 1 bag of portland cement (1506 kg/cu.m) and density of dry sand (1602 kg/ cu.m)
* volume of mortar horizontal joint = 5row x 0.2m x 1.0m x 0.01m = 0.01cu.m
* volume of mortar vertical joint = 4row x 0.2m x 1.0m x 0.01m = 0.008cu.m
* total mortar required = 0.01 + 0.008 = 0.018cu.m
3. using the commonly used ratio for making a good mortar 1:3,
* quantity of cement required = 1/4 (density of cement x total vol of mortar) = 1/4(1506x0.018) = 6.78kgs
* quantity of dry sand required = 3/4 (density of dry sand x total vol of mortar) = 3/4(1602x0.018) = 21.63kgs

Is This Answer Correct ?    36 Yes 12 No

how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / s.dhote

how much quantity of blocks,cement and sand is required to complete 1sq.m of cc solid blockswork.size 2'*8"*8".also what is the cement sand ratio commonly used?

Is This Answer Correct ?    33 Yes 10 No

how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / er.k.pratabchandran

BLOCK SIZE :390*190*190MM(ON MUSCAT)

WITHOUT C.M NOOFBLOCK IS=1/(0.39*0.19*0.19)=71NOS

WITH C.M NOOFBLOCKS IS=1/(0.40*0.20*0.20)=62.5NOS

C.M=(71-62.5)=8.5NOS*(0.39*0.19*0.19)=0.119CUM

REQUIREMENT FOR C.M1:5=1/5*1440=288KG=5.76BAGS/CUM

FOR 0.119CUM=5.76*0.119=0.68BAGS(WITHOUT WASTAGE)

FOR SAND C.M=1/5*1.57(FACTOR FOR FINESAND)=0.314CUM

FOR 0.119CUM=0.314*0.119=0.037CUM=1.30CFT(0.037*35.315=1.30CFT)

Is This Answer Correct ?    23 Yes 5 No

how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / alpesh patel

how many cement& sand consumption for 600*200*200 light weight block (1:5 ratio)in 1m3

Is This Answer Correct ?    23 Yes 6 No

how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / saikat roy

Above all 2 ans should be factored with 1.4 for wet to dry volume conversion.

Is This Answer Correct ?    15 Yes 6 No

how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / p mathan kumar b.e.,

1. I have used light weights block sizes 590*200*200
2. Volume Mortar = (42.3-37.8) *0.59*0.2*0.2
3. 1.06 cu.m
4. Mortar ratio 1:4
5. Volume of cement = 1.06*1/5=0.0213 cu.m*1440=30.58 kg
6. Volume of sand= 1.06*4/5=0.848 cum

Is This Answer Correct ?    3 Yes 0 No

how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / janani

Blocks-37 nos
Cement-1.6 bags
Sand-9.88cft

Is This Answer Correct ?    4 Yes 2 No

how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork...

Answer / betonaloka

Do you want to see the consumption of cement in each building block on the beton aloka site?

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

For M25 concrete ,what is the maximum compressive strength at 28 days ?

6 Answers   L&T, Techno Builders,


Cube tests of concrete are failed at 7 days and 28 days.What is your next action?

8 Answers   AppLabs, Parsvnath,


how to calculate the number of bricks for 10'x10' wall?

8 Answers   STR Builders,


What kind of soil has what bearin for pile work? eg sand with high water table collapses faster, black cotton soil is ideal, sand leads to more wear and tear of the boring consumables, rock takes longer and require rock augers etc etc

1 Answers   HCC,


How to calculate sand , cement quantity for 23mm thk brick work(10x10)

0 Answers  






what is compressive strength of bricks?

11 Answers   L&T,


How to calculate unit weight of concrete for m40 grade.

0 Answers   ERRA,


What is the Maximum & Minimum size of rod using on the column?

5 Answers  


In the cement the compound quickest to react with water

2 Answers  


in m45 what does m and 45 refers

4 Answers  


which type of binding wire gauge using gulf countries

2 Answers   Al Rashed,


In a beam tension is always at the bottom but sometimes when we design using staad we get more number of rebars at the top compression zone Why?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)