how much quantity of blocks, cement and sand is required to
complete 1sq.m of CC Hollow blockwork. Size-16"x8"x8". Also
what is the cement sand ration commonly used?

Answer Posted / er.k.pratabchandran

BLOCK SIZE :390*190*190MM(ON MUSCAT)

WITHOUT C.M NOOFBLOCK IS=1/(0.39*0.19*0.19)=71NOS

WITH C.M NOOFBLOCKS IS=1/(0.40*0.20*0.20)=62.5NOS

C.M=(71-62.5)=8.5NOS*(0.39*0.19*0.19)=0.119CUM

REQUIREMENT FOR C.M1:5=1/5*1440=288KG=5.76BAGS/CUM

FOR 0.119CUM=5.76*0.119=0.68BAGS(WITHOUT WASTAGE)

FOR SAND C.M=1/5*1.57(FACTOR FOR FINESAND)=0.314CUM

FOR 0.119CUM=0.314*0.119=0.037CUM=1.30CFT(0.037*35.315=1.30CFT)

Is This Answer Correct ?    23 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Curing time for 1)R.C.C slab 2)B.W 3)Plastering

1638


PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.

1987


psc girder detail

2705


1.what type of the rock is most suitable for wet mix macadam in construction of road? 2.what is the highest maximum dry density and optimum moisture content can be acheive by using most suitable crush rock?

2017


Describe the role of independent Quantity surveyor?

2442






How to arrive d*d/162 , for finding the kg per meter , wt of steel

1393


How to calculate laplength for 3 floors

1342


what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????

1623


What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?

691


How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure

1761


What are your goals?

2095


what is right & short method of measurement of slab&beam

1576


How to calculate quanty of steel in four leg stirrups?

1445


What is the effect of a building collapse?

615


 Describe a time when you anticipated potential problems and developed Preventive measures

2799