how much quantity of blocks, cement and sand is required to
complete 1sq.m of CC Hollow blockwork. Size-16"x8"x8". Also
what is the cement sand ration commonly used?
Answer Posted / p mathan kumar b.e.,
1. I have used light weights block sizes 590*200*200
2. Volume Mortar = (42.3-37.8) *0.59*0.2*0.2
3. 1.06 cu.m
4. Mortar ratio 1:4
5. Volume of cement = 1.06*1/5=0.0213 cu.m*1440=30.58 kg
6. Volume of sand= 1.06*4/5=0.848 cum
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
How does a traffic light signal work ?
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
(Project Management Topic) What are the important criteria in the successful realization of the project?
Describe Briefly The Various Methods Of Concrete Curing?
Trapezoidal section footing calculation of Volume & its Area
For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions
How many Sft of Level Plaster per Kg
Why should you consider yourself fit to be hired by jindal steel.
Draw the cross section of a boundary wall and label its part with detailing?
Bitumen grades are 30-40,60-70, 80-100. what is mean by 30- 40
Stringer How many cm goes to landind
What are the delays in construction projects due to approvals from owners? How can we analyze them in different prospective? Whats their affects and effects on presently going work?
Explain what is progress payment?