Cube tests of concrete are failed at 7 days and 28
days.What is your next action?
Answers were Sorted based on User's Feedback
Answer / vaibhav jadhav
Any is code not give the clause regarding demolishing of
structure if cube fails in 28 days. but IS 456 & 516 give
the clause if strength of cube is less than FCK then
proceed for NDT Test i.e Rebound hammer if fail then go for
Ultrasonic test after all the NDT fail then proceed for
Core cutter also if U found result less then FCK then go
for Retrofitting with suggestion of consultant.
| Is This Answer Correct ? | 33 Yes | 2 No |
Answer / abhijit
ensist contractor to hold skilled man power with quallity
material. note the result in daily work progress and mark
on structure which is not as per specification. finally go
for NDT if also structure fails then we have to demolish &
reconstruct the same
| Is This Answer Correct ? | 37 Yes | 10 No |
Answer / nravindran
Go for NDTest, if it is not satisfied go for Core test that
is also failed go for concrete strengthing process As per
structural consultant comments
| Is This Answer Correct ? | 19 Yes | 4 No |
Answer / vimalsekar
Well. When Concrete cube test result fails at 28th day then
go for concrete core cutting and check the compressive
strength in it. Number of cores shall be as per the
engineer incharge's decision but should not be less than 3
nos. IS:456 says if the core test fails then go for load
test. IS : 456 also says that NDT can be done . But with
rebound hammer test only surface hardness will be known and
hence this test result is not reliable and hardly anyone
suggests for this test.
| Is This Answer Correct ? | 18 Yes | 3 No |
Answer / shafqat
Use concrete tester rebound hammer for strength after
calibration.
Perform test as per standard,if results is more than 100 %
of requirement by calibration graph of hammer continue the
structure.
| Is This Answer Correct ? | 11 Yes | 3 No |
Answer / kishorecivil
NDT testing has to be done and if it fails then go for
recto method that is strengthing of concrete and concern is
not demolish it's time taken and it will effect time and
finacial.
| Is This Answer Correct ? | 8 Yes | 7 No |
Answer / prabhakara rao.b
Go for NDT If it is not satisfied go for Core test that
is also failed go for there possibale demolisan that coloum
it is not possible we go for Restrengthing.
| Is This Answer Correct ? | 4 Yes | 3 No |
How many types of grades in concrete mixing
6 Answers White Horse Ventures,
Why ss Steel is not using in RCC concrete.
CORRECTION Kindly furnish the relation between 7 days strength & 28 days compressive strength of Cement Concrete cubes. Can you clarify whether the relation gets altered due to various WATER-CEMENT ratios and type of cements?
who to find building iron rod strenth
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.
how to take quantity of steel per cum in columns
2 Answers ERRA, Skyline Builders,
what is difference between long column and short column?
16 Answers L&T, Tomi Polytechnic,
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
What is the bar bending schedule
I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shuttering?
Dear Friends am S.PRABHU looking for job chnage i have wonderfull exposure to both Construction works & i have a experience 11 years if any found any suitable opening, please Contact 9986539249
what is the procedure of plastering..?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)