Answer / niranjan

Fieldbus (or field bus) is the name of a family of industrial computer network protocols used for real-time distributed control, now standardized as IEC 61158.
PROFIBUS (Process Field Bus) is a standard for field bus communication in automation technology.
The Profibus in his Process versiĆ³n (Profibus PA) is two wire (Twisted pair) for data and power.
fieldbus foundation is only for process (Mainly for instruments), Profibus is for process and automation (instruments, drives, I/O, motor controllers to PLC, PLC to PLC etc.).

Is This Answer Correct ?    15 Yes 1 No

Post New Answer

More Instrumentation Interview Questions

What are the different types of thermistors used in industries? How to the operation of typical thermistor?

0 Answers  


what is the standard controll pressure

1 Answers  


During valve sizing from all calculation you got flow coefficient CV 12,than what it means? like for selecting pressure transmitter if your MAWP is 12 bar than you select a capsule of max. 20 bar which cover your mawp 12 in same way for selecting control valve If CV is 12 than how we use it in selecting valve??????

1 Answers  


what is upstream and downstream in liquid flow?

6 Answers   Thermax,


what is Micro-switch and where it is used......?

7 Answers  






Can 2 transmitters be connected to Integral orifice meter taps? Does an integral orifice comes with 2 set of taps?

1 Answers  


what are the on/off valve precaution?

1 Answers   Reliance,


A valve in series with an orifice plate (DP transmitter), is aligned for constant pressure in the pipeline, if there is an error dx, How to align it in process.

0 Answers  


What is the difference between fire detector and smoke detector?

5 Answers  


What is the difference between HMI and SCADA?

2 Answers  


Why Ma signal is using for control system?

1 Answers   Petrofac,


Hello friends i need check lists of different instruments during the Erection and commissioning in thermal power plant.Please help me.My Mail id is naba02222@gmail.com/naba02222@rediffmail.com Thanks Nabakishore Biswal

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)