what is periode of deshuttering for different area of slab
Answers were Sorted based on User's Feedback
Answer / saiprasad malandkar
Deshuttering time as per IS-456-2000
IS 456-2000,clause-11.3.
Type of Formwork minimum period
a) Vertical formwork to columns, walls, beam 16-24 h
b) Soffitformwork to slabs (Props to berefixed immediately afterremoval of formwork) 3 days
c) Soffitformwork to beams (Propsto be refixed immediately afterremoval of formwork) 7 days
d) Propsto slabs: 1) Spanning up to 4.5 m 7 days
2) Spanning over4.Sm 14days
e) Props to beams and arches: 1) Spanning up to 6 m 14 days
2) Spanning over6 m 21 days
| Is This Answer Correct ? | 49 Yes | 0 No |
Answer / santhosh kumar
basically deshuttering of slab is in depend up on the mix
propotion of the concrete.and achived strength more than
75%.
like m15 is needed for deshuttering period is 21 days
we are using m20,for slabs need 14 days is enough.
in beams we are using m20 and above 10 ~14 days are
applicable in practcial.
for using post tension in the slab we are using m35
concrete in slabs it is deshutttered 7 ~ 8 days.(when the
portion is after stressed)
to calculate the concrete strength in lab take 3 cube of
concrete and tested in lab 3 cube average strength is
needed 75%.
| Is This Answer Correct ? | 59 Yes | 12 No |
Answer / nikunj faldu
yas, santhosh kumar statment is right, but that depend up
on span of slab also, bcos. the dead load of slab is bigest
fector efecting on deshuttering.
than second, almost people remove shuttering below the slab
and beam bottom are stay long time, unother give a support
on bottom and remove shutter, that's all right.
one more sugetion is if that wall shuttering so, u must be
remove after 24 to 36 hours.
| Is This Answer Correct ? | 26 Yes | 4 No |
Answer / harbans singh
It is also depends on whether in cold deshuttering required
more time.
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / nitin patil
What santosh kumar given answer is correct.but sometimes it is observed that for M20 grade slab deshuttering is done in 7-8 days.it depends on the material used also.
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / benny joseph
Solid slab 30cm thick x 1000 m2 deshuttering shall be how many days of after casting ( slab mix opc 380kg) 7days curing
| Is This Answer Correct ? | 0 Yes | 1 No |
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!
howto calculate the quantities of material used in fly ash brick after finding the volume??
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
what is the load bearing capacity of the scafolding pipe (50mm) and other.
Why are we providing crank in beam? Thanks.
HOW TO DETERMINE FOUNDATION DEPTH OF A MULTYSTORIED BUILDING. IS THERE ANY OTHER FORMULA EXCEPT RANKINE'S MINIMUM DEPTH FORMULA.
how much quantity a carpenter do shuttering per day
19 Answers Nexus Technologies, Tata Projects,
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
In case of a beam ,main steel is provided along the longer span because, bending moment is directly proportional to length but why in case of one way slab main steel is provided along shorter span while as bending takes place along longer span?comment
Grades of concrete
28 Answers Mittal Steel, UNOPS,
150mm bricks size how many use 4.14 m3
How do you convert wind speed into force?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)