what is periode of deshuttering for different area of slab
Answers were Sorted based on User's Feedback
Answer / saiprasad malandkar
Deshuttering time as per IS-456-2000
IS 456-2000,clause-11.3.
Type of Formwork minimum period
a) Vertical formwork to columns, walls, beam 16-24 h
b) Soffitformwork to slabs (Props to berefixed immediately afterremoval of formwork) 3 days
c) Soffitformwork to beams (Propsto be refixed immediately afterremoval of formwork) 7 days
d) Propsto slabs: 1) Spanning up to 4.5 m 7 days
2) Spanning over4.Sm 14days
e) Props to beams and arches: 1) Spanning up to 6 m 14 days
2) Spanning over6 m 21 days
Is This Answer Correct ? | 49 Yes | 0 No |
Answer / santhosh kumar
basically deshuttering of slab is in depend up on the mix
propotion of the concrete.and achived strength more than
75%.
like m15 is needed for deshuttering period is 21 days
we are using m20,for slabs need 14 days is enough.
in beams we are using m20 and above 10 ~14 days are
applicable in practcial.
for using post tension in the slab we are using m35
concrete in slabs it is deshutttered 7 ~ 8 days.(when the
portion is after stressed)
to calculate the concrete strength in lab take 3 cube of
concrete and tested in lab 3 cube average strength is
needed 75%.
Is This Answer Correct ? | 59 Yes | 12 No |
Answer / nikunj faldu
yas, santhosh kumar statment is right, but that depend up
on span of slab also, bcos. the dead load of slab is bigest
fector efecting on deshuttering.
than second, almost people remove shuttering below the slab
and beam bottom are stay long time, unother give a support
on bottom and remove shutter, that's all right.
one more sugetion is if that wall shuttering so, u must be
remove after 24 to 36 hours.
Is This Answer Correct ? | 26 Yes | 4 No |
Answer / harbans singh
It is also depends on whether in cold deshuttering required
more time.
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / nitin patil
What santosh kumar given answer is correct.but sometimes it is observed that for M20 grade slab deshuttering is done in 7-8 days.it depends on the material used also.
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / benny joseph
Solid slab 30cm thick x 1000 m2 deshuttering shall be how many days of after casting ( slab mix opc 380kg) 7days curing
Is This Answer Correct ? | 0 Yes | 1 No |
Cement proportion in Fly ash bricks and type of cement to be used ?
how to calculate cube strength in percentage
how to find steel quantity
What applicable rate of wct in bihar
how do we calculate wastage of steel in the site,what r the items to taken into account for wastage calculation?
How Many Brick in One Cubic Meter.
how to calculate sand, aggregate and cement in m25 concrete?
2 Answers CCL Products, Western Infrastructure,
What is stripping?
how to calculate cost for MS plate shuttering (show calculation/assumptions)
what is the weight of concrete for 1 cum?
15 Answers Dhenu Infrastructure, L&T,
how much cost of single coat 20mm thick plastering per sqre meter
What is componsation
0 Answers Nagarjuna Construction,