Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is periode of deshuttering for different area of slab

Answers were Sorted based on User's Feedback



what is periode of deshuttering for different area of slab..

Answer / saiprasad malandkar

Deshuttering time as per IS-456-2000


 IS 456-2000,clause-11.3.



Type of Formwork minimum period

a) Vertical formwork to columns, walls, beam 16-24 h

b) Soffitformwork to slabs (Props to berefixed immediately afterremoval of formwork) 3 days

c) Soffitformwork to beams (Propsto be refixed immediately afterremoval of formwork) 7 days

d) Propsto slabs: 1) Spanning up to 4.5 m 7 days
2) Spanning over4.Sm 14days

e) Props to beams and arches: 1) Spanning up to 6 m 14 days
2) Spanning over6 m 21 days

Is This Answer Correct ?    49 Yes 0 No

what is periode of deshuttering for different area of slab..

Answer / santhosh kumar

basically deshuttering of slab is in depend up on the mix
propotion of the concrete.and achived strength more than
75%.
like m15 is needed for deshuttering period is 21 days
we are using m20,for slabs need 14 days is enough.
in beams we are using m20 and above 10 ~14 days are
applicable in practcial.

for using post tension in the slab we are using m35
concrete in slabs it is deshutttered 7 ~ 8 days.(when the
portion is after stressed)
to calculate the concrete strength in lab take 3 cube of
concrete and tested in lab 3 cube average strength is
needed 75%.

Is This Answer Correct ?    59 Yes 12 No

what is periode of deshuttering for different area of slab..

Answer / nikunj faldu

yas, santhosh kumar statment is right, but that depend up
on span of slab also, bcos. the dead load of slab is bigest
fector efecting on deshuttering.
than second, almost people remove shuttering below the slab
and beam bottom are stay long time, unother give a support
on bottom and remove shutter, that's all right.

one more sugetion is if that wall shuttering so, u must be
remove after 24 to 36 hours.

Is This Answer Correct ?    26 Yes 4 No

what is periode of deshuttering for different area of slab..

Answer / harbans singh

It is also depends on whether in cold deshuttering required
more time.

Is This Answer Correct ?    3 Yes 1 No

what is periode of deshuttering for different area of slab..

Answer / nitin patil

What santosh kumar given answer is correct.but sometimes it is observed that for M20 grade slab deshuttering is done in 7-8 days.it depends on the material used also.

Is This Answer Correct ?    2 Yes 0 No

what is periode of deshuttering for different area of slab..

Answer / benny joseph

Solid slab 30cm thick x 1000 m2 deshuttering shall be how many days of after casting ( slab mix opc 380kg) 7days curing

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

how to calculate the quantity of steel used for construction..

1 Answers   Salam,


how many labour is required for 1cum of concrete?

6 Answers  


what formula used to find the length of triangle ring in column?

1 Answers   Hitech,


How to do rate analysis for concrete work including shuttering work?

0 Answers   DBM, Techno Solutions,


how to calculate cut length of re-bar in a circle . because we not place same length of re-bar in whole circle maximum in center and minimum at corner so how to calculate middle bars???

0 Answers   Student,


what is called Bulk Density of aggregate?

0 Answers   PBL,


What is a hatch patterns?

0 Answers  


What is the Null Point of chimney in Power Plant

0 Answers   Reliance,


std heights of c.p fitting from ffl like health faucet,wall mixer,shower arm,european commod,wall hanging commod etc.

1 Answers   Maples,


how to find quantity of concrete in PCC M15

0 Answers  


what is a minimum strength recommented for aerocon blocks?

2 Answers  


what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)