what is periode of deshuttering for different area of slab
Answer Posted / nikunj faldu
yas, santhosh kumar statment is right, but that depend up
on span of slab also, bcos. the dead load of slab is bigest
fector efecting on deshuttering.
than second, almost people remove shuttering below the slab
and beam bottom are stay long time, unother give a support
on bottom and remove shutter, that's all right.
one more sugetion is if that wall shuttering so, u must be
remove after 24 to 36 hours.
| Is This Answer Correct ? | 26 Yes | 4 No |
Post New Answer View All Answers
if 20mm aggregate is coming by weight 25 ton in a 10 wheeler hywa ,then what will be total volume of aggregate in cubic feet.
What is the force exerted by the tacoma narrows bridge?
How to fix toll charge for a particular vehicle at toll booths in a highway?
What is the use of offset command?
Which brick is best for construction ,either fly ash or AAC BLOCKS
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
how clculate excavated or backfilling quantity by simpson's rule
How much is the cover for slab?
why is M30 grade Concrete use for Foothing & Column M50
how we check the thickness and line of ceiling plaster.
What do you mean by bond? What are the different types of bonds?
How to compute minimum number of columns required for a site from area of site?
Difference between pre-tensioning and post-tensioning.