Answer / nil ratan adhya
180 degree bend means bar straightline or parallal line so cutting length actul dimentional length
Is This Answer Correct ? | 36 Yes | 9 No |
Answer / vishal
for 90degree is 2d for 180 degree how much is cutting length
please answer from vishal
Is This Answer Correct ? | 14 Yes | 5 No |
Answer / vinod kumar, sriharikota
GENERALLY 90DEGREES BEND IS 2D, 180DEGREES MEANS IT IS STRAIGHT BAR THE CUTTING LENGTH IS TAKEN INTO ORIGINAL LENGTH OF BAR.
Is This Answer Correct ? | 5 Yes | 3 No |
Answer / anvesh
the standard bending shape is U..
the minimum cuttin length for 90degres bend should be 4d. nd
it should not 3d
for better grip..
the total length reuired for hook is 12d measured starting
from the point the bar start to bend.
Is This Answer Correct ? | 3 Yes | 2 No |
Answer / amol pawar
For 135 180 and 90 degree bend hook length is 12D ,9D, 8D
Where D is diameter of bar
Is This Answer Correct ? | 0 Yes | 1 No |
Answer / narendra
for 90 degree 6*diameter of bar and for 180
degree 9*diameter of bar
Is This Answer Correct ? | 2 Yes | 5 No |
why red bricks used for brickbat coba
Unit weight of sand
what is the tool used at construction site for measuring cement, sand and blue metal in india.
How to evaluate the elastic modulus of soil from the plate load test result? for example ..one of test results are here Max. settement =4.56mm(at 900kPa) Residual settlement = 4.02mm Maximum pressure on soil 900kpa Soil bearing capacity 300kpa Plate diameter=300mm Thickness =25mm Soil description =Grey, clayey silty SAND with gravels and rock fragments
WHAT IS THE DIFFERENCE BETWEEN FACTOR OF SAFETY AND PARTIAL SAFETY FACTOR?
concrete cube strength if fail 1 no in 7 days .What is the solution
what should be the minimum cross sectional dimensions of column for any given loads????
at what pressure ply-wood is obtained by gluing wooden sheets
what is difference between bending and twisting
How to increse bearing capacity in soils (Stabilisation of soils)
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
What is the Compressive strength of concrete C40/20 at 7days