Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how can we decide where we have to DYn11 or other vector
group transformer

Answers were Sorted based on User's Feedback



how can we decide where we have to DYn11 or other vector group transformer..

Answer / ramachandran n

Vector Groups are the IEC method of categorizing the
primary and secondary winding configurations of 3-phase
transformers. Windings can be connected as delta, star
(wye), or interconnected-star (zig-zag). Winding polarity
is also important, since reversing the connections across a
set of windings affects the phase-shift between primary and
secondary. Vector groups identify the winding connections
and polarities of the primary and secondary. From a vector
group one can determine the phase-shift between primary and
secondary.
The first criterion to consider in choosing a vector group
for a distribution transformer for a facility is to know
whether you want a delta-star or star-star. Utilities often
prefer star-star transformers, but these require 4-wire
input feeders and 4-wire output feeders (i.e. incoming and
outgoing neutral conductors). For distribution transformers
within a facility, often delta-star are chosen because
these transformers do not require 4-wire input; a 3-wire
primary feeder circuit suffices to supply a 4-wire
secondary circuit. That's because any zero sequence current
required by the secondary to supply earth faults or
unbalanced loads is supplied by the delta primary winding,
and is not required from the upstream power source. The
method of earthing on the secondary is independent of the
primary for delta-star transformers.
The second criterion to consider is what phase-shift you
want between primary and secondary. For example, Dy11 and
Dy5 transformers are both delta-star. If you don't care
about the phase-shift, then either transformer will do the
job. Phase-shift is important when you are paralleling
sources - you want the phase-shifts of the sources to be
identical. If you are paralleling transformers, then you
want them to have the same the same vector group.
If you are replacing a transformer, use the same vector
group for the new transformer, otherwise the existing VTs
and CTs used for protection and metering will not work
properly.

Is This Answer Correct ?    40 Yes 7 No

how can we decide where we have to DYn11 or other vector group transformer..

Answer / gunasekaran

normally Dyn11 vector group using at distribution
system.because GT are YNd1 for neutralizing the load angle
between 11 and 1. we use Dyn1 at distribution system we r
using GT are YNd11. in some industries 6 pulse electric
drives are using due to this 5thharmonics will generate if
we use Dyn1 it will be suppress the 5th harmonics.

Is This Answer Correct ?    10 Yes 12 No

how can we decide where we have to DYn11 or other vector group transformer..

Answer / praween

Generally Vector group is configure the tranformer primary and seccodry winding with each other....these vector group are diffrent type like as dyn1,dyn11 ,dyn0,dyn6 .we understand the phase difference with niddle of clock..there are30 degree make between two..that means of dyn11 is delta winding laggs 30 degree from star winding of transformer....

Is This Answer Correct ?    0 Yes 4 No

how can we decide where we have to DYn11 or other vector group transformer..

Answer / eng. ahsan rassam

DEPENDING ON TYPE SYSTEM VOLTAGE FOR EXAMPLE IF WE HAVE
33KV AND 11KV WE CHOOSE VECTR GROUP DYN11. AND IF WE WANT
TO OPRET TWO OR MORE TRANSFORMER OR GENERATOR IN PRALLER WE
MUST CHOSSE SAME VECTOR GROP.

Is This Answer Correct ?    6 Yes 18 No

Post New Answer

More Electrical Engineering Interview Questions

Why Two Transformers aside shoud be supperated by concreted wall?

5 Answers  


how much earth resistance consider to commissioning the transformer?

3 Answers   Deccan Cements,


can any tell me how to do wiring connection in L&T 3ph 4wire E301 CT operated energy meter, what is P1,P2,P3,P0. M1,M2,M3, L1,L2,L3.

2 Answers   Bhartiya International,


What's difference between a400amps lt contactor and a400amps lt circuit breaker

3 Answers   Indian Railways,


how you configure motorvision relay (L&T make)from DCS

0 Answers   Ispat,


why should we india maintain frequency of 50 Hz.

8 Answers  


what is KA rating and how can we choose switchgears on applications

0 Answers  


What is basic difference between Soft Starters And VFD drives?

19 Answers   IBM,


what is the size(sq.mm) of these conductors dog,rabbit,tiger,panther,mush,

8 Answers   Power Grid,


Differentiate between kirchhoff’s first law and kirchhoff’s second law?

0 Answers  


what is joule?

2 Answers  


Mechanism of Wye Delta Starter?

2 Answers   ABB,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)