In material determination how you configure the system
should propose when product A is not available then only
system substitute with product B. If A is available 60%
quantity. How do you do in the situation?
Answers were Sorted based on User's Feedback
Answer / rohan
Hi,
This can be achieved by Automatic Product Selection in
Material Determination. Use Substitution Reason 0004/0006
(Automatic Product Selection) while creating the master
data for material determinantion.
After creating the master data with the above mentioned
susbtitution reason maintain the list of products in proper
sequence i.e. Product A,B,C..System will first check for
the availability of Product A first and then substitute
with the next material if product A is not available.Incase
if Product A is partially available, then the system will
use all the available quantities of Product A first and
then fill the remaining quantities with Product B.
Thanks
Is This Answer Correct ? | 8 Yes | 1 No |
Answer / monty
hi rohan ,cn you please tell where we maintain the list of
PRODUCT A,B,C....
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / karun
In this situation product A rounds the quantity 50% in
material master send it 1st delivery
remaining 50% substitute product B in place of A in another
delivery date
Is This Answer Correct ? | 0 Yes | 3 No |
While I am creating a customer in ship to party account group you have shipping and billing partner function tab pages, client wants to shift all important fields in billing like payment terms, incoterms , and tax classification into shipping tab page. He wants only shipping partner function only, how does you customize?
What is Partner type?Example it?
in Variant configuration what are all the questions we can expect in interviews?
My client want EK02 as mandatory we are using MTO scenarios. I have selected EK02 in Pricing Procedure as Mandatory but when i try to create sales order it says condition record is missing for EK02 when i try to Create condition record VK11 and enter EK02 it say no access sequence for EK02. Their is no access sequence in condition type EK02 in spro Please help me out with EK02 as i want it MANDATORY. Need steps to configure it...
Hi Experts,Is SAP Solution Manager an inbuilt software within SAP System or do you have to purchase it from outside?Please answer this question asap.... Looking forward for your express reply...I have interview within 1-2 days. So, give reply to this query asap.. I would be very grateful to you for your timely help.Thanks in advance. Regards
In credit management if horizon period exceeded the warning message will not shown during sales order...how?
What is the difference between Intercompany(order type) invoice type and normal ordertype. What kind of different condition types used. What are the differences.
I have two different terms of payment one is grace period of 10 days and other one is 15 days. Now I have two set of materials, one is set A and other one is Set B. If a customer initiate a sales order for Set B materials then the customer should get terms of payment of 15 days or else I should get 10 days terms of payment in sales order. How can I overcome this.
do you know shipping condition? from where it is come?
with two sales organization, two distribution channel and two division howmany sales areawe can prepare.
describe organizational structure of sd?
Does sap transportation management have load planning capabilities? : transportation management