Answer / fazil
As per I.S. 13920 Vertical bars of Columns shall be lapped
in regular zone (Mid-height ) only
and it should be staggered i.e. not more than 50% of bar can
be lapped at one section. In
addition to that minimum clear vertical distance between
lapped bars shall be 0.25 times lap
length.
| Is This Answer Correct ? | 13 Yes | 2 No |
Answer / arunachalam subiramani
In my 20 years exp vertical member lap should be 50times dia of the bar should provided
| Is This Answer Correct ? | 5 Yes | 0 No |
Answer / waseem athar
there are two types of zone in column,
1). no lap zone
2). splice zone
the lap length is provided in splice zone of column..
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / bilal ali khan
iN ZONE A That is in between
for example
colimn dimensionj all in mm
lenght=1000
breadth=300
height=2440
so we will take lenght 1000 and take it from bottom and take it from top of bottom
left space in between is 440mm it is zone a
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / waseem athar
Lap should be provided in splice zone or mid zone of column and it should be 50 times of dia of bar.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / neelam saroj
In column Lap length should be provided at mid height only
as per IS.
and it should be staggered prperly it means not more 50% of
of bar can be lapped at one section.
=}in general practice wht i do,
lap length should be above the slab at some distace or
below the beam at certain distance.
| Is This Answer Correct ? | 0 Yes | 0 No |
how to calculate steel in slabs ?
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
List out the diameter of series of bar for beam, column, slab and footing?
what is mix design?
How to find weight of 1cu.m concrete in varies grades? and giive calculation.
Define What is Civil Engineering?
what is the difference between two way slab and flat slab? what is the benifits of flat slab?
how many re use can use shutting material. timber ? ply? steel? plastic? fibre? aluminium? Doka?
What should be the 28 days cube strength for M-25 grade concrete?How it is connected with acceptance criteria of fck+3 as per IS 456-2000 and why?
4 Answers IVRCL, NCC, Simplex, Tata Steel Limited,
how much quantity of paint is required for 1 square meter wall for single and double coat..?
Mujhe koi ye bta do ki 1.54 hi ku lete h material ki quantity niklne ke liye Sab jgha dhund liya bt samj nhi aaya mujhe koi alag aalag krke smjao ki cement m aggr. Dust m itne % wet or dry % hoti h fir kaise kaise 1.54 aaya kha se aaya smjao koi pls m confuse hu my calling nd wts app no. Is +919034604938
Which prize is the alternative to the NOVEL Prize?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)