Answer Posted / fazil
As per I.S. 13920 Vertical bars of Columns shall be lapped
in regular zone (Mid-height ) only
and it should be staggered i.e. not more than 50% of bar can
be lapped at one section. In
addition to that minimum clear vertical distance between
lapped bars shall be 0.25 times lap
length.
| Is This Answer Correct ? | 13 Yes | 2 No |
Post New Answer View All Answers
Which is the direction of negative angle?
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
brickwork labour rate per cum ?
How many types of slabs are there & how to design it?
what is floating slab foundation?
In cement concrete how to check a quality of material also proportion of material at site ?
What is the quantity of metal 1 & metal 2 to be used in 100 cft concrete?
1m square 20mm plastering how much of water need curing work
What are the alternate material for steel, Sand and aggregate
How will be cutting in timber plate size 600*400 column size
find the discharge of water through a horizental venturimeter having 400mm dia at the inlet main and 150mm dia at thorat.if the diffrential gauge between inlet and thorat shows a pressure head of 25cm mercury. assume coefficient discharge 0.98 and specfic gravity of mercury as 13.6.
i am laying a base of dimensions 6.5feet by 7feet by 1.25 feet depth how many bags of 25kg cement and how many bags of 25kg sand will i need
in plate load test what is the thickness of plate 20mm 5mm 50mm none
What is pre-stressed concrete?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?