Answer / d. baby
size of footing x depth of footing = earthwork qty
a x b x d = qty
total earthwork - isolated footing qty = earth filling
| Is This Answer Correct ? | 15 Yes | 3 No |
Excavation > is l x b x h
but filling is total excavation - pcc-rcc of footing up to NGL
| Is This Answer Correct ? | 7 Yes | 1 No |
Answer / ramcharan
Earth quantity = aria isolated footing + working margin
Earth filling quantity = earth quantity _ isolated footing
| Is This Answer Correct ? | 4 Yes | 1 No |
Minimum and maximum size of the building components
what is pqc
sir, how to calculate steel per 1 m2
What is creep ,deflection and shrinkage in concrete
what is coping?
11 Answers GKC Projects Limited GKCPL, Technical Construction, Vijai Electricals,
What is the development length given in pile?
what is grade slabs
rcc floor to floor 4m. in column reinforcement where we provide lap in exact location.
difference between deep and shallow well?
whats is the Indian standard ratio for mix design M5 M10 M15 M20 M25 M30 M35 AND M40???
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
What is the difference between single reinforcement
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)