How to calculate stirrups cutting length in columns
Answers were Sorted based on User's Feedback
1) let cover for column be 40mm (as u have not mentioned)
formula to determine cutting length of stirrup is given below
cutting length= (2A+2B)+(24D)
A=LONGER LENGTH OF COLUMN-2XCOVER=400-40X2=320MM
B=SHORTER LENGTH OF COLUMN-2XCOVER=250-40X2=170MM
D= DIAMETER OF STIRRUP BAR IN MM
therefore
cutting length=2X320+2X170 + 24X8 =1172MM=1.172 meter
2) given cover 25mm (as u have mentioned)
formula to determine cutting length of stirrup is given below
cutting length= (2A+2B)+(24D)
A=LONGER LENGTH OF BEAM-2XCOVER=400-25X2=350MM
B=SHORTER LENGTH OF BEAM-2XCOVER=200-25X2=150MM
D= DIAMETER OF STIRRUP BAR IN MM
therefore
cutting length=2X350+2X150 + 24X8 =1192MM=1.192 meter
NOTE SLAB COVER HAS NOTHING TO DO WITH CAL.OF STIRRUPS
3) ASSUME cover 30mm (as u have NOT mentioned)
formula to determine cutting length of stirrup is given below
cutting length= (2A+2B)+(24D)
A=LONGER LENGTH OF COLUMN/2 -COVER=400/2-30=170MM
B=SHORTER LENGTH OF COLUMN-2XCOVER=250-30X2=190MM
D= DIAMETER OF STIRRUP BAR IN MM
therefore
cutting length=2X170+2X190 + 24X8 =912MM=0.912 meter EACH
Generally term stirrups are used for lateral tie for beams while term ring is used for columns.calculation of length for stirrups & ring are same. Stirrups length depend upon size of column/beam,cover,dia of stirrup's bar.Nominal cover is measured from outer face of stirrups to concrete face.Although this cover at site is measured from outer face of main bar.If cover for beam is 25 mm then, for 90 degree hook for 600x400 mm column & 10 mm dia bar as per IS Code 2502 length will be=2[(600-2x25)+(400-2x25)]+20x10mm=2000...
If there are four bar of 20mm dia on 600 mm face then for central stirrup of this side will be=[600-25-25-(20/2)-(20/2)]/3=176.66 between centre of two bars of this face,now add (20/2)+(20/2) so that outer face to outer face of 20 dia bar=196.6say 197mm. same way other side of central stirrups are calculated & then add 20 times bar dia.Add 24 xdia of bar for 135 degree hook
In IS code formula=2(A+B)+20 x bar dia. A & B are internal distance between stirrup side.
Is This Answer Correct ? | 9 Yes | 2 No |
Answer / sfz ans
above answer plus bent deductions at every bent (IS 2502)= cutting length.
ie: for columns (2A+2B)+(24D)-(kDx4)
k= 2 upto 25mm tor steel
Is This Answer Correct ? | 3 Yes | 2 No |
Wats the formula of eccentric footing and how was calculated from concrete qty
how to do rate analysis for P.C.C 1:4:8 for 2.83cum(100cft)
2 Answers Unity Infraprojects,
How much quantity water should be placed in one cubic meter area?
how can we calculate costing of a project per sqft/sqm
1 Answers Associate Consultant, AVT, L&T,
Hi Dudes, I have completed B.E Civil with two years experience in Highway& Bridges. One year experience in Site field & One year experience in Planning & Billing Dept. I am willing to work in abroad, i am having passport and all..So if anybody knows about foreign vacancy pls inform me..Ph:9994050979 & Mail Id: Simacivil1988@gmail.com
What is the frequency of sampling for the materials of cement,Fine aggregate, Coarse aggregate .and refer which code
0 Answers IVRCL, Techno Art Constructions,
In barbending schedule why is o.42*D is taken. Means why o.42 only???
Father of "reinforced cement concrete"?
When brick size is 3x5x9" , what would be the number of Brick requirement for 100 sqft area of 5" width?
What are the Noms/8hr for Concrete Work for Mason,Carpenter,Steel Fixer
How to layout the site plot ? Method with explation
Coarse aggregate & fine aggregates are called inert material when used in RCC work because------