Answer Posted / neelam saroj
In column Lap length should be provided at mid height only
as per IS.
and it should be staggered prperly it means not more 50% of
of bar can be lapped at one section.
=}in general practice wht i do,
lap length should be above the slab at some distace or
below the beam at certain distance.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How to calculate density of 40 mm coarse aggregate, in mixing ration 1:1.5:3? Please explain calculation for density
Slump Values for works?
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
Design a rectangular channel.
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
what is the type of earthing
how much shouid be the rate for ready mix concrete per cubic meter
How do you maintain water pressure?
How to calculate the load of partion in flat slab if we use brick?
mix design procedure for 1:6 cement mortar
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
five benefits of using standard terminology in the measurement process
what is meant by shear center?????
what is pile and deam foundation
what is total volume of ingredients used in concrete accordingly