Answer / surendra
As-IS is the document in which the exsiting procedure of the claint mention and the To-Be is the document in which how the claint wants to implement the sap in their organisation.
Is This Answer Correct ? | 15 Yes | 0 No |
Answer / durgesh m. kadam
In SAP this is a second phase out of five.
In this phase we creates the BBP (Business Blue Prints) into
2 parts
1st AS-IS and 2nd TO-BE.
In AS-IS we mentions business flow or activities of business
what company using.
&
In TO-BE we mention how your business look in SAP. (And
additional activities if company wants)
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / punitthakur001
When A client provide a business blueprint he mentions that
what will the change in new system(Implemention). If there
is no change from last system(Legacy system) called AS-is
but if there is change in new system(Implemention) it will
called TO-BE.
Is This Answer Correct ? | 5 Yes | 3 No |
Answer / siva
as is document:as is document will prepire client employees as per requirement this document submit to implementation partner team.
to be document: to be document will prepire implementation partner team based on as is document.
Is This Answer Correct ? | 2 Yes | 0 No |
what is the 'o' and '9' level dunning? can any one please specify the names of each 9 dunning level?
Usually how many abapers in a project?
Explain the terms segment and cycle?
How is intrest calculation on arrears for customers posted to GL Accounts
We had two controling areas with different Fiscal years. A year later we changed the FY so both Controlling areas now have same fiscal year. we want to get rid of one controlling area and bring all the company codes into one controlling area. What is the fastest and safest way to do it?
What are account assignment models? : co-pa
after entering (transation data) in the company code if our clint want to change the company code what is the procedure to change..
Lets say for a product there exists three production versions. Explain the process how you would go about creating a mixed cost estimate?
How do you maintain the number range in production environment? Do you directly create it in the production box or do you do it by means of transport?
Dear Please send me a T-Code with description for FICO.
Can we re issued a canceled cheque in SAP?
Hi Dear Friends, I am Sridhar, M.com, age is 50, working as a Finance Manager in a software company. I need your clarification, shall i enter as a SAP FICO consultant in this age, Please advice.