Answer / souagata bangal
In 150x150x150mm cube the dimension 150mm is match with the pressure plate dimension.If it is less than 150mm the total pressure distribution is not as per spesification and it will show more than the cube value.If the dimension is grater than 150 mm ,the pressure distribution will not to the whole surface of the cube.
Is This Answer Correct ? | 27 Yes | 5 No |
Answer / sjtbehera
Because as per IS standard the compressive strength is
taken as per these specimen
Is This Answer Correct ? | 29 Yes | 9 No |
Answer / sanjay tewatia
the test on this dimension is done because it is specified in is coding system, and also because the varieing pressure of concert will not rises in less then the 100mm area and it will not give the actual positioning of the spreading area and to varies the whole strength of each substance mixed in it to give its full volume
Is This Answer Correct ? | 7 Yes | 5 No |
Answer / deepak baviskar
Basically, the force supplied by a
concrete compression machine is a
definite value. For normal concrete
strength application, say below 50MPa,
the stress produced by a
150mmx150mmx150mm cube is
sufficient for the machine to crush the
concrete sample.
Is This Answer Correct ? | 1 Yes | 1 No |
Answer / h.k.chanchal
In RCC like M15,M20 suffix is result of compressive
strength of 150x150x150 mm cube sample.
Is This Answer Correct ? | 9 Yes | 16 No |
for solid cement brick without fly ash,we use dust,6mm,12 mm jelly,water my question is what Proportion we mix dust,6mm,12 mm jelly,water ? for good strength brick.
Will water damage concrete?
How to calculate the quantity of cement,sand,aggregate for the area L*B*T are 15.24 m*21.36m*0.12m in the ratio 1:2:4 can any ine explain in detail by using formulas. Thanks in advance
where you provide on column
what is IS CODE in concrete tiles
what is the name of coarse sand which is used in making of concrete
i Have Completed a Intermediate Vocational (Construction technology) with Bridge course ,iam elegible to join in Institute of Surveyors(india).
what is diffrence between catchment area,watershed and basin?
WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?
Defination of civil engineering
is ther any formule for w/c ratio
say the propotions of different concrete mix desidn(M20 M15 M25 M25 M30)