HOW to calculate Rate analysis of M15 GRADE DESIGN MIX RATIO
1:2.5:5 WITH 40MM Size aggregates for 1 cumtr.
Answers were Sorted based on User's Feedback
Answer / mohsin
Using a M15 Grade Ratio is 1:2.5:5 & Quantity Is 1m3
Now Add 1.52% Dry Volume In Total Quantity
So 1*1.52=1.52
1.52/8.5=0.178
0.178/0.03472=5.15 Approximate Cement bags.
Sand=0.178*2.5
=0.44m3
Aggricate=0.178*5
=0.89m3
Cost Of Labour Cost Of Material
--------------- ------------------
Mason- 450rs Cement=220*5.15= 1133 rs
Helper-210*2= 420rs Sand=400*0.44= 198 rs
Bhisti= 180rs Aggricate=620*0.89= 551.8 rs
------------------- --------------------------------
Total rs= 1050 Total Rs = 1882.8 Rs
Now Consider the 10% of total quantity...
And 10% Contractors profits
Is This Answer Correct ? | 13 Yes | 5 No |
when we calculate concrete volume in footing the column along with footing up to the ground level is also taken or not ?
what is the hanekom repairing material after concreting work
How many number of bars used in circular columns? Explain WHY?
how to prepare the bar bending schedule for a given rcc material?It will be more helpful if you explain me with an example?
what does 1 in 30 or 1 in 40 mean when constructing camber in roads.
in design case of structural member best suitrable percentage of steel limit is what
If 40 backlogs are cleared m finally with 65 percent marks . Am I eligible to get visa to US
what"s the formula find the cement consumption for brick work 12 thick wall 1 m2?
Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)
0 Answers L&T, Shoba Devlopers,
what is pouring and explain
Please tell me vasthu room sizes. Thanks.
What is Gsb tollens ?