Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ?

Answers were Sorted based on User's Feedback



How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / santosh singh

the procedure to calculate quanity is given below

eg. if cement mortar ratio is ( 1:6)

suppose 1 cum of cement mortar work is to be done

then add 60% extra for voids & cavities in case of plaster

then total volume of work = 1 + 60/100 x1 =1.6 cum
quantity of cement in cum = 1.6 / (1+6)= 1.6/7=0.228 cum
but as we know cement is available in market in 50 kg
bags (volume of 50kg cement is = 0.0347 cum)

thu quantity of cement in bags = 0.228/0.0347= 6.57 bags

quantity of sand in cum= 0.228 x 6 =1.36 cum



eg. if cement mortar ratio is ( 1:4)

suppose 1 cum of cement mortar work is to be done

then add 60% extra for voids & cavities in case of plaster

then total volume of work = 1 + 60/100 x1 =1.6 cum
quantity of cement in cum = 1.6 / (1+4)= 1.6/5=0.32 cum
but as we know cement is available in market in 50 kg
bags (volume of 50kg cement is = 0.0347 cum)

thu quantity of cement in bags = 0.32/0.0347= 9.22 bags

quantity of sand in cum= 0.32 x 4 =1.28 cum

this is exact procedure.you can calculate for any ratio of
cement & mortar

Is This Answer Correct ?    303 Yes 69 No

How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / guppi chandra sekhar

Calculation of materials for 1cum of 1:6 Cement Mortar by
Volumetric method:
Specific Gravity of Cement = 3.15 ; Density of Cement =
1440kg/cum
Specific Gravity of Sand = 2.6 ; Density of Cement =
1550kg/cum @ 5% moisture
First of all we have to calculate yield of 1 cement bag
(50kg) mixed in 1:6
Volume of Cement = (50/1440) = 0.03472cum
Volume of Sand mixed = 6 X 0.03472 = 0.208cum (contains 5%
moisture)
Volume of only sand = 95% of 0.208 = 0.198 cum
Absolute volume of Cement = 50kg / (3.15X1000) = 0.016 cum
Absolute volume of sand = Weight of sand / (2.6 X 1000) =
(0.198 X 1550) / (2.6 X 1000) = 0.118 cum
Let volume of water added = 30litres = 0.03 cum
Moisture present in the sand = (0.208 - 0.198) = 0.01 cum
Total volume of water = 0.03 + 0.01 = 0.04 cum
Let, Moisture content in the mortar = 2% of yield
Let, yield = Y
(1-2%)Y = Absolute volumes of (Cement + Sand + Water) =
0.016 + 0.118 + 0.04 = 0.174 cum
Total Yield Y = 0.174 / 0.98 = 0.178 cum
1bag of 50kg Cement produces = 0.178 cum of 1:6 Cement
Mortar with 0.208cum of Sand @ 5% Moisture and 30 litres of
water.
Therefore, 1 cum of 1:6 Cement Mortar requires :
Cement = 1bag X 1/ 0.178 = 5.62 bags
Sand = 0.208 X 1 / 0.178 = 1.17 cum
Water = 30 X 1 / 0.178 = 168 .5 litres

Is This Answer Correct ?    55 Yes 21 No

How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / arjun

1:4 (or) 1:6

Is This Answer Correct ?    30 Yes 17 No

How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / saritha

how to calculate cement and sand quantities in cement
mortar as 1:3?

Is This Answer Correct ?    20 Yes 8 No

How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / sagar

how to calculate water for brick work , plaster , flooring,
emergency.

Is This Answer Correct ?    16 Yes 8 No

How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / osbert (civ eng. student maker

take an example 1:4, total ratio(1+4)is 5. assume total
volume of mortar required is 10cubic metre. this will
contain 1/5of10=2cubic metre of cement and 4/5of10=8cubic
metres of sand. density of cement as 1440kg/m3, mass of
cement will be 2x1440=2880kg and number of bags
2880/50=57.6bags. note
(i) 50kg is mass of 1 bag of cement.
(ii)other irregularities like covering voids, reduction in
volume/shrinkage due to setting of cement etc should be
considered by factoring the total volume by say 1.4.
(iii)for water use about 30% of the raw volume of sand and
cement.

Is This Answer Correct ?    17 Yes 14 No

How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / v.kapil

I think Mr. kamlesh is right
The considraion of voides for mortor is 25% and rest method
is same as our conventionel menthod, but for plaster 30 %
should be increase for undulation ( uneven wall surface)
also so total dry volumn is 1 + 25% + 30% = 1.55 Cum

Is This Answer Correct ?    16 Yes 15 No

How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / prakash

Calculation Method
Plastering with CM 1:5 12 mm thick - 10 m2

Area to be Plastered = 10 m2

Thickness of mortar Layer = 12 mm = 0.012 m

Volume of mortar required = 10 x 0.012 = 0.12 m3

Add 15 percent allowance for undualation of surface & wastage = 0.018 m3

so, total volume of Mortar Required = 0.138 m3 say 0.14 m3

sand required for 0.14 m3 of CM 1:5 = 0.14 m3

cement required for 0.14 m3 of CM 1:5 = 0.14/5 = 0.028 m3

wt of cement required = 0.028 x 1440 = 41 kg

Is This Answer Correct ?    24 Yes 24 No

How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / guppi chandra sekhar, au colle

Calculation of materials for 1cum of 1:6 Cement Mortar by
Weighing method:
Specific Gravity of Cement = 3.15 ; Density of Cement =
1440kg/cum
Specific Gravity of Sand = 2.6 ; Density of Cement =
1550kg/cum @ 5% moisture
First of all we have to calculate yield of 1 cement bag
(50kg) mixed in 1:6
Weight of Cement = 50kg
Weight of sand mixed = 6 X 50 = 300kg (contains 5%
moisture also)
Approximate volume of sand = 300 / (2.6 X 1000) = 0.12 cum
(contains 5% moisture also)
Weight of only sand = 95% of 300kg = 285 kg
Absolute volume of Cement = 50kg / (3.15X1000) = 0.016 cum
Absolute volume of sand = Weight of sand / (2.6 X 1000) =
285 / (2.6 X 1000) = 0.11 cum
Let volume of water added = 25 itres = 0.025 cum
Moisture present in the sand = 300 - 285 = 15kg = 15
litres = 0.015 cum
Total volume of water = 0.025 + 0.015 = 0.04 cum
Let, Air content in the mortar = 2% of yield
Let, yield = Y
(1-2%)Y = Absolute volumes of (Cement + Sand + Water) =
0.016 + 0.11 + 0.04 = 0.166 cum
Total Yield Y = 0.166 / 0.98 = 0.17 cum
1bag of 50kg Cement produces = 0.17 cum of 1:6 Cement
Mortar with 0.12 cum (equals to 300kg) of Sand @ 5%
Moisture and 25 litres of water.
Therefore, 1 cum of 1:6 Cement Mortar requires :
Cement = 1bag X 1/ 0.17 = 5.88 bags
Sand = 300 X 1 / 0.17 = 1765kg (or) equivalent to 0.71 cum
by volume
Water = 25 X 1 / 0.17 = 147 litres

Is This Answer Correct ?    9 Yes 10 No

How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ?..

Answer / jitender mishra

For planter 20mm thickness
area 100m2
= 100*.02= 2m3
20% for wide of brick work & westage.
=2*.2= 2.4m3
Bluk 1.3
=2.4*1.3=2.99m3
Ratio
1:2
=1/3*2.99=.996m3(cement)
For bag .996/.03496=28.45bagscement
for slarry 1sqmtr =2kg cement.
So 100sqmtr 200kg/50 =4 bags
total cement qty =28.45+4= 32.45 bags cement
Sand
=2.99*2=5.98m3 sand
Note: this qty condider for only for plaster.


Is This Answer Correct ?    10 Yes 14 No

Post New Answer

More Civil Engineering Interview Questions

Any bopdy tell me how to prepare rate analysis for Centering and shuttering for RAFT FOUNDATION, SUSPENDED FLOORS, STAIR CASES, RETAINING WALLS, SHEAR WALL and COLUMNS

1 Answers  


A ground is nonengginered fill 15 years back; how we can find the level of consolidation and bearing capacity

2 Answers  


how much M-25 steel reinforcement per cubic meter in commercial building as per IS code

2 Answers   Shyam Indus Power,


How does a traffic light signal work ?

0 Answers   KCP,


How can u prepare mix design for concrete?

2 Answers   L&T, Lafarge,


what is plate load test??

4 Answers  


what is the weight of concrete cube of 1ft*1ft*1ft? tell me weight in pound & in KG

3 Answers  


explain yourself?

1 Answers   Infosys, Omaxe, Siscom, TCE,


What is gauge and gage?

6 Answers   L&T,


Totally how many Grades of Concrete are there? and Explain Briefly?

2 Answers   Reliance,


how much aggregate need for 1:4:8 p.c.c in 1sqm area?

5 Answers  


How much do you want salary?

13 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)