How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ?
Answer Posted / jitender mishra
For planter 20mm thickness
area 100m2
= 100*.02= 2m3
20% for wide of brick work & westage.
=2*.2= 2.4m3
Bluk 1.3
=2.4*1.3=2.99m3
Ratio
1:2
=1/3*2.99=.996m3(cement)
For bag .996/.03496=28.45bagscement
for slarry 1sqmtr =2kg cement.
So 100sqmtr 200kg/50 =4 bags
total cement qty =28.45+4= 32.45 bags cement
Sand
=2.99*2=5.98m3 sand
Note: this qty condider for only for plaster.
| Is This Answer Correct ? | 10 Yes | 14 No |
Post New Answer View All Answers
Explain the difference between shear and tensile strength.
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m
What is progress payment?
how can calculate the compressive strength of concrete cylinder by water cement ratio ?
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
Concrete cover for slab, column, beam and footing?
how to tie 10 legged stirrups
How to take labor charges for construction of 1cum of concrete?
what does the track parameter mean in staad.pro?
How do you convert wind speed into force?
What is the Maximum %age of Steel in columns and beams ?
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.
how to calculate the length diamond shaped striupps in column
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor