Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ?

Answer Posted / osbert (civ eng. student maker

take an example 1:4, total ratio(1+4)is 5. assume total
volume of mortar required is 10cubic metre. this will
contain 1/5of10=2cubic metre of cement and 4/5of10=8cubic
metres of sand. density of cement as 1440kg/m3, mass of
cement will be 2x1440=2880kg and number of bags
2880/50=57.6bags. note
(i) 50kg is mass of 1 bag of cement.
(ii)other irregularities like covering voids, reduction in
volume/shrinkage due to setting of cement etc should be
considered by factoring the total volume by say 1.4.
(iii)for water use about 30% of the raw volume of sand and
cement.

Is This Answer Correct ?    17 Yes 14 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Which are the top apps for you civil engineering?

1076


In csae of hume pipes NP stands for Non Pressure bur what does it really mean?

2265


std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30

1966


How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)

1998


Which brick is best for construction ,either fly ash or AAC BLOCKS

960


What is difference between engineering stress and true stress?

1111


Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.

1714


Why joints are provided?

1072


What is critical path method (c.p.m)?

1105


Formula of mid span bar

1870


what else we can add rather than admixture in concrete to reduce the cement quantity?

6096


a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer

2502


what are the challenges of being a team leader and a supervisor?

3805


Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––

2343


Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish

2572