Answer / will
Say cement sand ratio is 1:6
calculate the quantity of mortar in 1m2 of brickwork, say
it is 0.01912.
just devide by the ratio considering 60% for wastage, say
0.01912/1*0.6=0.01147 volume of cement in the mortar.
Divide the total volume of cement by 0.0345 which s the
volume of 1 bag, say 0.01147/0.0345=0.33257/m2*number of
m2, say 100m2=34bags.
Is This Answer Correct ? | 5 Yes | 9 No |
Answer / dilshad akthar
ratio: 1:4
for 1 m3,cement= 1/(1+4)=1/5=.2m3,let it be .2+.6*.2=.32
quqntity of cement:
.32*1440(unit wt of cement)*1=460.8
bags rqd= 460.8/50(1 bag)=9.2````let be 10;
sand requred
4*.2*1=.8m3
typical one load==5m3
Is This Answer Correct ? | 0 Yes | 4 No |
Answer / t.chandrasekar
the unit weight of cement is 1440kg/m3.
for 1 m3 of 1:1 cement mortor the reuirement of sand is 1m3
and cement will be 1part of sand that is 1 m3 thus weight
of cement required is 1x1440kg/m3=1440 kg.
for 1 m3 of 1:2 cement mortor the reuirement of sand is 1m3
and cement will be 1/2 part of sand that is 0.5 m3 thus
weight of cement required is 0.5x1440kg/m3=720 kg.
for 1 m3 of 1:4 cement mortor the reuirement of sand is 1m3
and cement will be 1/4 part of sand that is 0.25 m3 thus
weight of cement required is 0.25x1440kg/m3=360 kg.
for 1 m3 of 1:6 cement mortor the reuirement of sand is 1m3
and cement will be 1/6 of part sand that is 0.5 m3 thus
weight of cement required is 1/6x1440kg/m3=240 kg.
Is This Answer Correct ? | 44 Yes | 49 No |
Answer / kamlesh patidar
in cement morter the void between sand and cement is less
and take 25% total wet volume of water.take 10 cu m wet
volume of morter increse 25% than total volume of dry
material 12.5 cu m . if we find the material in 1:6 morter
than 12.5/(1+6)
cement=1.78 cu m sand=1.78*6=10.71cu m
Is This Answer Correct ? | 11 Yes | 17 No |
Answer / syed mahaboob hussain
the procedure to calculate quanity is given below
RATIO (1:6)
NOTE = 1:6: 0.55(Water) = + (7.55)
CEMENT = 1m3/7.55 x 1 = 0.132m3 (No of Kg = 0.132 x 1506 =
198.792kg)
Sand = 1m3/7.55 x 6 = 0.794m3 (No of Kg = 0.132 x 1650 =
437.250 kg)
Water = 1m3/7.55 x 0.55 = 0.072 m3 ( No of Kg = 0.072 x
1000 = 72liter)
Is This Answer Correct ? | 20 Yes | 52 No |
what"s the purpose of dry lean concrete(DLC)and where it"ll be use it?
Can a wave happen in the middle of the ocean like in the movie poseidon 2006?
how to calculate the cement, sand, coarse aggregate required for one cubic meter of concrete?
What is the material consumption- cement,sand,tiles etc for Toilet dado?
what is moment-curvature relationship in semi rigid connections??
how can we calculate cutting length of a column ring (300 x 600)
16 Answers AVL, Manchanda, Vardhman,
what is mean by quality in terms of construction
What you understand by building codes?
what happens when the curing is not done properly for structures ??
for 100sft of Cement plastering ratio 1:6 How much quantity of cement and sand required.
6 Answers J.K. Organization, L&T,
What is limit state method and working stress method and ultimate method
Who name us Engineer & Why?