How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ?
Answer Posted / kamlesh patidar
in cement morter the void between sand and cement is less
and take 25% total wet volume of water.take 10 cu m wet
volume of morter increse 25% than total volume of dry
material 12.5 cu m . if we find the material in 1:6 morter
than 12.5/(1+6)
cement=1.78 cu m sand=1.78*6=10.71cu m
Is This Answer Correct ? | 11 Yes | 17 No |
Post New Answer View All Answers
HOW MANY BAGS OF CEMEMT USED IN PER M2 OF PARTITION WALL
how to calculate weight of 1.8 cum of aggregate
what is shuttering co efficient?
a butt weld is specified by
Minimum concrete cover in slabs, columns, beams, foundation and other st?
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
What is difference between engineering stress and true stress?
How much quantity of rod binding work by a rod binder per day
What is thumb rule in quantity and cost estimation of a residential building?
explain fie benefits of using standard terminology in the measurement process
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
Explain the importance of moment of inertia?
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.