How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ?
Answer Posted / dilshad akthar
ratio: 1:4
for 1 m3,cement= 1/(1+4)=1/5=.2m3,let it be .2+.6*.2=.32
quqntity of cement:
.32*1440(unit wt of cement)*1=460.8
bags rqd= 460.8/50(1 bag)=9.2````let be 10;
sand requred
4*.2*1=.8m3
typical one load==5m3
| Is This Answer Correct ? | 0 Yes | 4 No |
Post New Answer View All Answers
What is min thickness,min grade of conc & age of PQC ?
What are the different softwares used for cad?
What is the force exerted by the tacoma narrows bridge?
What is meant by dimensioning?
Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot
significance of specific surface area of particles?
What are moment of inertia and its importance in civil engineering?
If specific gravity of cement is less than 3.15 what is the cause?
Minimum concrete cover in slabs, columns, beams, foundation and other st?
how to calculate the strength of rebound hammer test reading in building construction ?
how will remove spiderweb cracking in plaster ? what the reasone of make it ?
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
What is the release of lien?