How to configure Make-to-order in sd. Tell me the process
step by step
Answers were Sorted based on User's Feedback
Answer / rajiv trivedi
Make to Order Steps in SAP
Create materials with required views - MM01
Create Bill of Materials (BOM) - CS01
Create Routing to Finished material - CA01
Create sale order - VA01
Run MRP - MD50
View the planned orders created - MD04
Convert component planned order to PR (PR will show a/c assgn cat as M)
MD04Convert semi finished planned order to PR (PR will show a/c assgt category M & item cat."L")
-
MD04-Convert component PR into PO for external procurement - ME21
Goods receipt with reference to sale order - MIGO
View the stock (sale order stock) - MMBE
Create subcontract PO with reference to semi finished PR - ME21N
Maintain storage location to the subcontractor - SPRO
Transfer goods to Subcontractor (movement type 311 +E) - MB1B / MIGOStock will be updated
Receive goods from Subcontractor with movt type 101 (543 will be taken to the component &subcontractor storage location to be entered) - MIGOReconciliation of challan
Goods issue to the production with movement type 261 - MB1A / MIGO
Confirmation of Production order - CO15
Goods receipt against Production order with movement type 101 - MB31/MIGOOrder settlement for Production order - KO88
Delivery of Finished products - VL01N
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / tulsiprasad4
Create mm01 with configurable materia type + Item category
group
should be 0001 + materia group 00804.select purchasing view
+ Availability ck shoud be 02.
Now create, VA01 n see item category shud be TAK + see
requirement shud be KE. schedule line shud be CP.
Now do initilize d stock with 561 & stock indicator SHD BE E
Is This Answer Correct ? | 5 Yes | 6 No |
Answer / q. nguyen
SAP provides steps-by-steps configuration for
Make-to-Order(MTO) with Variant Configuration(VC), and MTO
without VC. My answer would be referring to the SAP Best
Practices for MTO with/without VC.
Is This Answer Correct ? | 5 Yes | 8 No |
Hi Experts, Have you worked on any Interfaces like BADI‘s & BAPI’s? I do not want any theoretical answers? Just give me the Business Scenarios which are related to BADI’s & BAPI’s and how did you worked with ABAPer along with detailed procedure & analysis? I do not want any coding / programming part if any I am only interested in SAP SD Interface with BADI & BAPI and how did you meet the requirement of client by the ABAPer? If any coding is involved then explain in simple steps if it is simple only? I have been asked this question in a recent interview? Explain BADI‘s & BAPI’s with your real time Project examples & Business Scenarios along with the ABAP coding & the simple solution he gave you for your requirement? It’s Urgent!!!!!!This is most frequently asked question in almost in all interviews. So, I request you to provide solutions to above question as early as possible? Your timely help would be greatly appreciated? Thanks in advance Regards
What is the difference between task and change request?
In Third Party sales ME21 A/C assignment G/L a/c 893010 is set(proposed by the system)but in MIRO it is giving error that G/L A/C 893010 is set is not relevant for Tax,how to solve the problem?
9. Any three major issues faced in the support project? what kind of issues they were
In v/08 what is the significance of assigning pricing type like carry out new pricing etc.
How data collected from client side before implementing the project
hello, i have 4 years of exp in marketing so some of my friends suggested to learn sap sd so i want to know about the market position of sap sd i.e., present and future so let me know about the openings of sap sd. whether it is feasible or not to learn sap sd now.. with regards, ravikiran 9989362083..
what is the mean of rebate processing
In Credit Management what are the update groups in SAP SD? What is the importance of this update groups in Credit Mgmt? Briefly tell me the difference between different update groups and which update group your client is using at present? Please reply asap... Urgent!!!! Waiting for your response eagerly... Thanks in advance
where can i find all the customers in my company and what is the t code
How to same in period and FY by using Transaction code MMPV
what is the sla in your current project? what is the billing rate? how to answer these questions? i explained about the ticketing levels p1,p2,p3,p4 but the interviewer was not satisfied with the answer what does he mean by sla in the project??